License
- License number
- 736277
- Status
- Clear
- Classifications
- A General Engineering Contractor
- C-8 Concrete Contractor
- C-12 Earthwork and Paving Contractor
- C-21 Building Moving/Demolition Contractor
- C-34 Pipeline Contractor
- Business type
- Corporation
- Issued
- May 20, 1997
- Expires
- May 31, 2027
- Workers' compensation
- Workers' Compensation Insurance — Travelers Property Casualty Company Of America
- Contractor's bond
- $25,000 — American Contractors Indemnity Company
- DIR public works registration
- Registered through Jun 30, 2027
From the California Contractors State License Board (CSLB) public license file, last updated Apr 3, 2026. Verify license #736277 on CSLB's License Check.
California public works
G F GARCIA & SONS INC appears on 35 public works projects registered with the California Department of Industrial Relations, 11 of them as the prime contractor, for 5 awarding bodies between 2023 and 2026. Projects it led total $334,339 in reported contract value.
| Date | Project | Awarding body | Role | Contract amount |
|---|---|---|---|---|
| Aug 31, 2026 | Grading for seatrainStorm drain & flood control | Cal Poly State University, San Luis Obispo | Prime | $28,176 |
| Jul 7, 2026 | Transformer relocationElectrical, low voltage & AV | Cal Poly State University, San Luis Obispo | Prime | $15,000 |
| Jun 16, 2026 | Del Mar Phase 2 ModernizationBuildings & facilities | San Luis Coastal Unified School District | Subcontractor | $2,561,512 |
| May 15, 2026 | Laguna Middle School StairwayBuildings & facilities | San Luis Coastal Unified School District | Subcontractor | $74,892 |
| May 5, 2026 | CL Smith Phase 2 ModernizationBuildings & facilities | San Luis Coastal Unified School District | Subcontractor | $6,942,000 |
| Dec 16, 2025 | MBHS & SLHS Artificial Turf FieldsParks, landscape & fields | San Luis Coastal Unified School District | Subcontractor | $5,594,923 |
| Dec 12, 2025 | Repair Water Transmission Lines Water MaWater | Cal Poly State University, San Luis Obispo | Prime | $41,338 |
| Dec 4, 2025 | Maintenance supportOther | Cal Poly State University, San Luis Obispo | Prime | $10,000 |
| Nov 4, 2025 | Pcv steam repairDemolition & site work | Cal Poly State University, San Luis Obispo | Prime | $11,375 |
| Jun 20, 2025 | Demo and excavation of existing vault foDemolition & site work | Cal Poly State University, San Luis Obispo | Prime | $21,639 |
| Jun 17, 2025 | Los Osos Middle School Phase 1B Amnd. 02Buildings & facilities | San Luis Coastal Unified School District | Subcontractor | $15,724,558 |
| Jun 3, 2025 | Los Ranchos Phase 1 Amnd. 02Buildings & facilities | San Luis Coastal Unified School District | Subcontractor | $1,399,666 |
| May 30, 2025 | Laguna Middle Portable PrepBuildings & facilities | San Luis Coastal Unified School District | Prime | $66,550 |
| May 27, 2025 | SLO 1300 Sewer Line & MH ReplacementSewer & wastewater | San Luis Obispo County Community College District | Prime | $55,000 |
| May 20, 2025 | Laguna Middle Phase 1B Amnd. 02Buildings & facilities | San Luis Coastal Unified School District | Subcontractor | $19,277,369 |
| May 6, 2025 | Pacific Beach High School New CampusBuildings & facilities | San Luis Coastal Unified School District | Subcontractor | $14,041,621 |
| Mar 4, 2025 | Video Broadcast ProjectOther | Cal Poly State University, San Luis Obispo | Subcontractor | $1,447,562 |
| Feb 27, 2025 | Switchgear Maintenance UpgradeElectrical, low voltage & AV | Cal Poly State University, San Luis Obispo | Prime | $49,700 |
| Feb 18, 2025 | Los Ranchos Phase 1 ModernizationBuildings & facilities | San Luis Coastal Unified School District | Subcontractor | $4,242,000 |
| Feb 5, 2025 | Pacer ProjectOther | Cal Poly State University, San Luis Obispo | Subcontractor | $2,191,671 |
| Jan 14, 2025 | Mt Bishop Warehouse RemodelBuildings & facilities | Cal Poly State University, San Luis Obispo | Subcontractor | $427,983 |
| Dec 18, 2024 | Exterior LED RetrofitElectrical, low voltage & AV | Cal Poly State University, San Luis Obispo | Prime | $15,000 |
| Oct 21, 2024 | EV Charger InstallationSolar, EV & energy | San Luis Coastal Unified School District | Subcontractor | $198,400 |
| Oct 15, 2024 | CL Smith & Sinsheimer Field RenovationParks, landscape & fields | San Luis Coastal Unified School District | Subcontractor | $1,827,030 |
| Aug 8, 2024 | CL Smith Phase 1 Amendment No. 02Other | San Luis Coastal Unified School District | Subcontractor | $4,138,988 |
Most recent 25 of 35. Contract amounts are the whole project's, as the awarding body reported them to DIR (reported since July 2024); a role is "Prime" when the awarding body registered the contractor on the project.
Awarding bodies it works for most
- San Luis Coastal Unified School District · 16 projects
- Cal Poly State University, San Luis Obispo · 15 projects
- San Luis Obispo County Community College District · 2 projects
- The City of Atascadero · 1 project
- County of San Luis Obispo · 1 project
Is this your business?
Claim it on Atriam to add your work photos, service area and a booking link, and to run calls, leads, estimates and invoices in one place — free.
Claim this business