SAFETY NETWORK INC
California contractor license #787285 · Fresno, Fresno County
License
- License number
- 787285
- Status
- Clear
- Classifications
- C-31 Construction Zone Traffic Control Contractor
- C-61/D-42 Non-Electrical Sign Installation
- Business type
- Corporation
- Issued
- Nov 13, 2000
- Expires
- Apr 30, 2028
- Workers' compensation
- Workers' Compensation Insurance — Berkshire Hathaway Homestate Insurance Company
- Contractor's bond
- $25,000 — Travelers Casualty And Surety Company Of America
- DIR public works registration
- Registered through Jun 30, 2027
From the California Contractors State License Board (CSLB) public license file, last updated Sep 29, 2026. Verify license #787285 on CSLB's License Check.
California public works
SAFETY NETWORK INC appears on 238 public works projects registered with the California Department of Industrial Relations, for 109 awarding bodies between 2016 and 2026.
| Date | Project | Awarding body | Role | Contract amount |
|---|---|---|---|---|
| Jun 18, 2026 | Merced Street ReconnectionPaving & streets | City of Fresno - Capital Projects Dept. | Subcontractor | $1,337,601 |
| Jun 8, 2026 | Willow Avenue Street ImprovementsPaving & streets | City of Clovis | Subcontractor | $1,069,839 |
| May 21, 2026 | Cedar Ave Roadway ImprovementsPaving & streets | City of Fresno - Capital Projects Dept. | Subcontractor | $1,469,234 |
| May 18, 2026 | CIP 24-16 Ashlan Ave Street ImprovementsPaving & streets | City of Clovis | Subcontractor | $1,395,801 |
| May 12, 2026 | Road 225 Ped Path ProjectPaving & streets | Madera County Public Works Department | Subcontractor | $887,213 |
| May 6, 2026 | RAYMOND ROAD STREET IMPROVEMENTSPaving & streets | City of Madera | Subcontractor | $443,261 |
| Apr 23, 2026 | Grantland WM Ext between Shaw & GettysbuWater | City of Fresno | Subcontractor | $1,159,574 |
| Apr 23, 2026 | WC00005Water | City of Fresno | Subcontractor | $1,193,060 |
| Mar 25, 2026 | Houghton Kearney Parking Lot ReconstructBuildings & facilities | Central Unified School District | Subcontractor | $377,046 |
| Feb 26, 2026 | Pave More Now Bid Package B-1Paving & streets | City of Fresno - Capital Projects Dept. | Subcontractor | $8,329,396 |
| Feb 9, 2026 | Herndon Avenue Street ImprovementsPaving & streets | City of Clovis | Subcontractor | $8,750 |
| Jan 13, 2026 | SULTANA AREA STORMWATER & RECHARGE PROJESewer & wastewater | County of Tulare State of California | Subcontractor | $485,465 |
| Jan 13, 2026 | Roads Program CIP 23-068 BP2Paving & streets | City of Turlock | Subcontractor | $6,127,005 |
| Jan 8, 2026 | Geotechnical Rd Reconstr Chestnut Ave.Design, inspection & consulting | County of Fresno Department of Public Works and Planning | Subcontractor | $25,418 |
| Jan 8, 2026 | Geotechnical Rd Reconstr. Cedar Ave.Design, inspection & consulting | County of Fresno Department of Public Works and Planning | Subcontractor | $25,418 |
| Jan 8, 2026 | Geotechnical Rd Reconstr. American Ave.Design, inspection & consulting | County of Fresno Department of Public Works and Planning | Subcontractor | $41,239 |
| Dec 16, 2025 | Cuddy Creek Box Culvert Improvements onStorm drain & flood control | County of Kern - Public Works | Subcontractor | $547,280 |
| Dec 11, 2025 | FIRE HYDRANT REPLACEMENT PROJECT.Water | Del Rey Community Services District | Subcontractor | $246,503 |
| Dec 9, 2025 | Mt. Whitney Ave. Road Reconstruction andPaving & streets | County of Fresno Department of Public Works and Planning | Subcontractor | $5,062,275 |
| Dec 9, 2025 | 2025 Corridor ProjectPaving & streets | City of Dinuba | Subcontractor | $4,296,502 |
| Nov 19, 2025 | Lassen Ave Union Pacific Railroad (UPRR)Paving & streets | City_of_Huron | Subcontractor | $489,000 |
| Nov 17, 2025 | Leland Lift StationSewer & wastewater | Windows Plus Construction, Inc | Subcontractor | $310,000 |
| Nov 6, 2025 | Almond Avenue ReconstructionOther | City of Sanger | Subcontractor | $822,412 |
| Nov 1, 2025 | CDT Segment Fiber F( 36)Other | California Department of Technology | Subcontractor | $12,995,625 |
| Oct 23, 2025 | Sidewalk Connectivity-PhIII 24651Paving & streets | City of Selma | Subcontractor | $379,145 |
Most recent 25 of 238. Contract amounts are the whole project's, as the awarding body reported them to DIR (reported since July 2024); a role is "Prime" when the awarding body registered the contractor on the project.
Awarding bodies it works for most
- County of Kern - Public Works · 16 projects
- City of Clovis · 16 projects
- City of Fresno · 13 projects
- County of Fresno Department of Public Works and Planning · 13 projects
- City of Fresno - Capital Projects Dept. · 11 projects
- City of Bakersfield · 6 projects
- California Department of Transportation (Caltrans) · 6 projects
- City of Turlock · 6 projects
- Clovis Unified School District · 6 projects
- Sanitation Districts of Los Angeles County · 5 projects
Is this your business?
Claim it on Atriam to add your work photos, service area and a booking link, and to run calls, leads, estimates and invoices in one place — free.
Claim this business