MONTEREY ENVIRONMENTAL SOLUTIONS AND SERVICES
California contractor license #988797 · Monterey, Monterey County
License
- License number
- 988797
- Status
- Clear
- Classifications
- B General Building Contractor
- C-22 Asbestos Abatement Contractor
- Business type
- Corporation
- Issued
- Dec 2, 2013
- Expires
- Dec 31, 2027
- Workers' compensation
- Workers' Compensation Insurance — Berkshire Hathaway Homestate Insurance Company
- Contractor's bond
- $25,000 — Atlantic Specialty Insurance Company
- DIR public works registration
- Registered through Jun 30, 2027
From the California Contractors State License Board (CSLB) public license file, last updated Jul 24, 2026. Verify license #988797 on CSLB's License Check.
California public works
MONTEREY ENVIRONMENTAL SOLUTIONS AND SERVICES appears on 47 public works projects registered with the California Department of Industrial Relations, 2 of them as the prime contractor, for 27 awarding bodies between 2022 and 2026. Projects it led total $374,048 in reported contract value.
| Date | Project | Awarding body | Role | Contract amount |
|---|---|---|---|---|
| May 12, 2026 | Marina Vista ES-Campus Mod., Phase 2Electrical, low voltage & AV | Monterey Peninsula Unified School District | Subcontractor | $2,152,726 |
| Apr 14, 2026 | MLK - Modernization, Phase 2 #8365Plumbing & restrooms | Monterey Peninsula Unified School District | Subcontractor | $2,370,875 |
| Mar 3, 2026 | Watsonville ADA RenovationsBuildings & facilities | Cabrillo College | Subcontractor | $176,681 |
| Mar 2, 2026 | Market Street Senior CenterPaving & streets | City of Santa Cruz Public Works Engineering | Subcontractor | $314,119 |
| Dec 31, 2025 | Emergency City Hall Restroom RepairsPlumbing & restrooms | City of Salinas - (PUB WORKS) | Prime | $25,048 |
| Oct 23, 2025 | Jade Street Park Restroom RenovationPaving & streets | City of Capitola | Subcontractor | $484,000 |
| Oct 6, 2025 | Fire Hydrant ReplacementWater | Marina Coast Water District | Subcontractor | $211,600 |
| Sep 29, 2025 | MACSA DemolitionDemolition & site work | Alum Rock Union Elementary School District | Prime | $349,000 |
| Jul 21, 2025 | Low Barrier Navigation Housing Site WorkDemolition & site work | County of Santa Cruz | Subcontractor | $1,465,741 |
| Jul 2, 2025 | D.A. Porath Water Main RelocationWater | County of Santa Cruz DPW | Subcontractor | $186,000 |
| May 27, 2025 | Monte Vista TK-8 Covered Walk RepairsRoofing | Monterey Peninsula Unified School District | Subcontractor | $200,049 |
| May 13, 2025 | Fire Station 1 Restrooms/Showers Reno.Plumbing & restrooms | City of Watsonville | Subcontractor | $594,831 |
| May 13, 2025 | MLK Modernization, Phase 1 #8363Parks, landscape & fields | Monterey Peninsula Unified School District | Subcontractor | $1,510,000 |
| May 13, 2025 | Monterey Adult School - Mod., Phase 1Electrical, low voltage & AV | Monterey Peninsula Unified School District | Subcontractor | $750,600 |
| Apr 8, 2025 | Olson ES - Modernization #8276Demolition & site work | Monterey Peninsula Unified School District | Subcontractor | $2,431,000 |
| Apr 8, 2025 | Ord Terrace ES - Campus Imp. #8119Demolition & site work | Monterey Peninsula Unified School District | Subcontractor | $6,200,000 |
| Feb 25, 2025 | Accessibility Impvts for Closter Park BlParks, landscape & fields | City of Salinas - (PUB WORKS) | Subcontractor | $320,225 |
| Feb 11, 2025 | FORT ORD DUNES SPOther | DEPARTMENT OF PARKS AND RECREATION-PARK OPERATIONS | Subcontractor | $32,202,082 |
| Feb 11, 2025 | Monterey HS - Emergency Water IntrusionBuildings & facilities | Monterey Peninsula Unified School District | Subcontractor | $293,460 |
| Jan 9, 2025 | 3100-075 Theater Arts Bldg A Rm A0212Plumbing & restrooms | University of California Santa Cruz | Subcontractor | $38,670 |
| Oct 22, 2024 | Salinas Fire Station No. 1 RenovationBuildings & facilities | City of Salinas Fire Department | Subcontractor | $3,532,250 |
| Sep 18, 2024 | Harbor High School Wellness CenterBuildings & facilities | Santa Cruz City Schools | Subcontractor | $1,440,537 |
| Sep 11, 2024 | Greenfield Library Roof ReplacementRoofing | County of Monterey Public Works, Facilities and Parks | Subcontractor | $355,209 |
| Sep 4, 2024 | C23720008 - Resource Office ImprovementsRoofing | Department of Parks and Recreation - Monterey | Subcontractor | $1,549,380 |
| Sep 4, 2024 | APR1801-1 Phase 1 ReconstructionPaving & streets | City of Marina | Subcontractor | $7,222,217 |
Most recent 25 of 47. Contract amounts are the whole project's, as the awarding body reported them to DIR (reported since July 2024); a role is "Prime" when the awarding body registered the contractor on the project.
Awarding bodies it works for most
- Monterey Peninsula Unified School District · 14 projects
- County of Santa Cruz · 4 projects
- City of Salinas - (PUB WORKS) · 3 projects
- Pajaro Valley Unified School District · 2 projects
- City of Monterey · 2 projects
- County of Santa Cruz DPW · 1 project
- County of Monterey Public Works, Facilities and Parks · 1 project
- City of Soledad · 1 project
- Santa Cruz City Schools · 1 project
- Salinas City Elementary School District · 1 project
Is this your business?