Calexico Unified School District
278 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Calexico, Imperial County. Reported contract value: $122,121,672.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 2 | $405,285 |
| 2025 | 7 | $3,376,806 |
| 2024 | 6 | $83,586,409 |
| 2023 | 23 | $34,753,172 |
| 2022 | 8 | — |
| 2021 | 21 | — |
| 2020 | 6 | — |
| 2019 | 9 | — |
| 2018 | 6 | — |
| 2017 | 42 | — |
| 2016 | 56 | — |
| 2015 | 69 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 91
- Buildings & facilities · 55
- Parks, landscape & fields · 37
- Electrical, low voltage & AV · 22
- Roofing · 15
- Paving & streets · 14
- Demolition & site work · 12
- HVAC & mechanical · 10
- Painting & flooring · 6
- Plumbing & restrooms · 4
- Fire & life safety · 4
- Sewer & wastewater · 3
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| A & N QUALITY BUILDERS INC | 4 | $1,743,093 |
| I V MECHANICAL INC DBA R & K AIR CONDITIONING | 1 | $286,810 |
| SYLVESTER ROOFING COMPANY INC | 1 | $118,475 |
| TRUELINE CONSTRUCTION & SURFACING INC DBA TRUELINE | 1 | $34,272 |
| TRI-CO FLOORS | 1 | $20,857 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| May 14, 2026 | Welding Shop Modernization-MechanicalHVAC & mechanical | I V MECHANICAL INC DBA R & K AIR CONDITIONING | $286,810 |
| May 14, 2026 | Roof Replacement at Calexico High SchoolRoofing | SYLVESTER ROOFING COMPANY INC | $118,475 |
| Dec 22, 2025 | Calexico High School Trailer RemovalFire & life safety | — | $74,500 |
| Dec 11, 2025 | Kitchen Electrical at Mains ElementaryElectrical, low voltage & AV | — | $12,200 |
| Aug 14, 2025 | ADA Site Improvements at Various SitesDemolition & site work | A & N QUALITY BUILDERS INC | $406,379 |
| Aug 14, 2025 | FRC Modular Building Site ImprovementsDemolition & site work | A & N QUALITY BUILDERS INC | $512,870 |
| May 27, 2025 | Classroom ReflooringPainting & flooring | TRI-CO FLOORS | $20,857 |
| May 22, 2025 | Calexico HS and Kennedy Gardens PavingPaving & streets | — | $890,000 |
| Mar 13, 2025 | Kennedy Gardens TK Bldg. Phase IIDesign, inspection & consulting | — | $1,460,000 |
| Aug 26, 2024 | Calexico High School-GreenhouseSewer & wastewater | A & N QUALITY BUILDERS INC | $382,175 |
| Aug 26, 2024 | Calexico High School WindscreensBuildings & facilities | TRUELINE CONSTRUCTION & SURFACING INC DBA TRUELINE | $34,272 |
| Aug 8, 2024 | Kennedy Garden Elementary School TransitBuildings & facilities | — | $728,293 |
| May 23, 2024 | District Wide Shade Structures ExteriorPaving & streets | A & N QUALITY BUILDERS INC | $441,669 |
| May 23, 2024 | Calexico High School Measure QParks, landscape & fields | — | $82,000,000 |
| Feb 14, 2024 | CHS 9th Gym Wall PadsBuildings & facilities | — | — |
| Nov 30, 2023 | Tennis Court Restoration at Calexico HigOther | — | — |
| Nov 26, 2023 | CHS A4 - 16 Classroom Modular Bldg, PhasBuildings & facilities | — | — |
| Nov 12, 2023 | Calexico High School A4Buildings & facilities | — | — |
| Nov 9, 2023 | District-Wide Telecor Clock/Paging ManagOther | — | — |
| Sep 20, 2023 | Electrical Wiring for the Installation oElectrical, low voltage & AV | — | — |
| Sep 18, 2023 | Window Replacements at the Weight Room aBuildings & facilities | — | — |
| Aug 16, 2023 | CHS Varner Gym BleachersBuildings & facilities | — | — |
| Aug 16, 2023 | CHS BleachersBuildings & facilities | — | — |
| Aug 15, 2023 | Dool Elementary School Rewire ElectricalElectrical, low voltage & AV | — | — |
| Aug 1, 2023 | Rockwood Modular RepairsBuildings & facilities | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.