125 public works projects registered with the California Department of Industrial Relations, 2012–2026 · Hughson, Stanislaus County. Reported contract value: $5,101,316.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 11 | $1,659,236 |
| 2025 | 14 | $3,116,495 |
| 2024 | 8 | $325,584 |
| 2023 | 10 | — |
| 2022 | 5 | — |
| 2021 | 15 | — |
| 2020 | 8 | — |
| 2018 | 6 | — |
| 2017 | 9 | — |
| 2016 | 15 | — |
| 2015 | 20 | — |
| 2012 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 39
- Other · 19
- HVAC & mechanical · 12
- Painting & flooring · 12
- Parks, landscape & fields · 11
- Paving & streets · 7
- Roofing · 6
- Demolition & site work · 4
- Electrical, low voltage & AV · 4
- Plumbing & restrooms · 3
- Design, inspection & consulting · 2
- Fire & life safety · 2
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| CHAMPION INDUSTRIAL CONTRACTORS INC | 3 | $171,403 |
| MESA ENERGY SYSTEMS INC | 2 | $857,239 |
| PARK PLANET | 2 | $319,356 |
| ENVIROPLEX INC | 2 | $298,770 |
| CONTROL SYSTEMS SERVICES | 2 | $134,747 |
| ROMANA INC | 2 | $127,630 |
| STONCOR GROUP INC | 2 | $53,875 |
| BARHAM INC DBA BZ CONSTRUCTION | 1 | $309,627 |
| ADVANCED ROOFING | 1 | $251,012 |
| JOAQUIN PAINTING INC | 1 | $180,450 |
| B T MANCINI CO INC | 1 | $138,766 |
| THP Mechanical LLC | 1 | $125,875 |
| BANKS GLASS COMPANY | 1 | $74,765 |
| BOYER CONSTRUCTION | 1 | $74,699 |
| RUMBLE TREE INC | 1 | $35,525 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 9, 2026 | HHS New Gym HVAC repairsDesign, inspection & consulting | CHAMPION INDUSTRIAL CONTRACTORS INC | $125,003 |
| May 12, 2026 | HHS Campus Paint Project phase 1Painting & flooring | JOAQUIN PAINTING INC | $180,450 |
| Apr 14, 2026 | HHS Gym Upper Window ReplacementBuildings & facilities | BANKS GLASS COMPANY | $74,765 |
| Apr 14, 2026 | HHS Gym Gutters and DownspoutsStorm drain & flood control | CHAMPION INDUSTRIAL CONTRACTORS INC | $30,443 |
| Apr 14, 2026 | HHS Gym Exterior RepairsBuildings & facilities | BOYER CONSTRUCTION | $74,699 |
| Apr 14, 2026 | Tree Removal HHS-AGParks, landscape & fields | RUMBLE TREE INC | $35,525 |
| Apr 14, 2026 | TK East Playground Structure replacementParks, landscape & fields | PARK PLANET | $169,998 |
| Mar 10, 2026 | Calshape VentilationHVAC & mechanical | MESA ENERGY SYSTEMS INC | $175,340 |
| Mar 10, 2026 | CALSHAPE PLUMBING FIXTURE REPLACEMENTPlumbing & restrooms | MESA ENERGY SYSTEMS INC | $681,899 |
| Mar 10, 2026 | EPOXY FLOORING 10-WING BATHPainting & flooring | STONCOR GROUP INC | $36,605 |
| Jan 14, 2026 | NEW FIRE MONITORING SYSTEM INSTALL ROSSOther | CONTROL SYSTEMS SERVICES | $74,509 |
| Dec 20, 2025 | Fox Elem. 2026 Relocatable ClassroomElectrical, low voltage & AV | — | $215,875 |
| Dec 20, 2025 | Ross Middle School. 2026 Relocatable ClaElectrical, low voltage & AV | — | $91,814 |
| Sep 23, 2025 | 40 Wing bathroom Epoxy FlooringPainting & flooring | STONCOR GROUP INC | $17,270 |
| Jul 18, 2025 | Hughson Elementary Playground EquipmentParks, landscape & fields | PARK PLANET | $149,358 |
| Jul 7, 2025 | 30 Wing HVAC ReplacementDesign, inspection & consulting | THP Mechanical LLC | $125,875 |
| Jun 10, 2025 | Temporary Student RestroomPlumbing & restrooms | ROMANA INC | $24,190 |
| Jun 10, 2025 | Temporary Student HousingBuildings & facilities | ROMANA INC | $103,440 |
| May 27, 2025 | Hughson Elementary – Fire Alarm SystemFire & life safety | CONTROL SYSTEMS SERVICES | $60,237 |
| Apr 11, 2025 | Fox 2026 Relocatable ClassroomPaving & streets | ENVIROPLEX INC | $154,991 |
| Apr 11, 2025 | Ross 2026 Relocatable ClassroomBuildings & facilities | ENVIROPLEX INC | $143,779 |
| Apr 1, 2025 | 2025 HES Relocatable classroomBuildings & facilities | — | — |
| Mar 12, 2025 | Hughson High Bond ModernizationHVAC & mechanical | — | $1,639,887 |
| Feb 13, 2025 | Hughson High 30 Wing Roof ReplacementRoofing | ADVANCED ROOFING | $251,012 |
| Jan 15, 2025 | Hughson High School Theater Seat ReplaceDemolition & site work | B T MANCINI CO INC | $138,766 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.