County of Marin DPW CPB-KP

15 public works projects registered with the California Department of Industrial Relations, 2016–2018 · San Rafael.

Projects by year

YearProjectsReported contract value
20184—
20174—
20167—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Paving & streets · 4
  • Buildings & facilities · 3
  • Other · 2
  • Plumbing & restrooms · 2
  • Fire & life safety · 1
  • HVAC & mechanical · 1
  • Electrical, low voltage & AV · 1
  • Painting & flooring · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Latest projects

DateProjectPrime contractorContract amount
Nov 5, 2018PRSPSB Windows ReplacementBuildings & facilities——
Sep 17, 2018County of Marin Juvenile Services CenterFire & life safety——
Apr 2, 2018Juvenile Hall CC FlooringPainting & flooring——
Feb 3, 2018MCJH IST FujitsuHVAC & mechanical——
Sep 7, 2017County of Marin Jail Reroofing Phase IIOther——
May 8, 2017Marin County Juvenile Hall New SecurityElectrical, low voltage & AV——
Mar 7, 2017PRSPSB Curb rampPaving & streets——
Feb 23, 2017PRSPSB Curb rampPaving & streets——
Nov 15, 2016N. San Pedro sidewalk repairPaving & streets——
Oct 26, 2016PRSPSB Lobby Entry ModificationsBuildings & facilities——
Oct 3, 2016Point Reyes Sheriff Substation AccessibiBuildings & facilities——
Aug 1, 2016Civic Center Room 419 Restroom AlteratioPlumbing & restrooms——
Mar 28, 2016Woodacre Fire Plumbing modificationsPlumbing & restrooms——
Mar 22, 2016N. San Pedro sidewalk repairPaving & streets——
Feb 8, 2016ball gameOther——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.