City of Lake Forest

9 public works projects registered with the California Department of Industrial Relations, 2016–2017 · Lake Forest.

Projects by year

YearProjectsReported contract value
20171—
20168—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Paving & streets · 3
  • Other · 2
  • Traffic & signals · 1
  • Parks, landscape & fields · 1
  • Buildings & facilities · 1
  • Electrical, low voltage & AV · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Latest projects

DateProjectPrime contractorContract amount
May 22, 2017Civic Center Parking DeckBuildings & facilities——
Dec 1, 2016Etnies Skate Park Facilities Painting &Parks, landscape & fields——
Oct 15, 2016LFSP Ph2-Handrails and StepsTraffic & signals——
Oct 15, 2016LFSP Ph2-Lighting Tot Lot & Batting CageElectrical, low voltage & AV——
Sep 9, 2016Portola Parkway RehabilitationPaving & streets——
Aug 8, 2016Portola Parkway Widening/Streetscape ImpOther——
Jun 13, 2016ADA Access Ramp Improvements, Phase 8Other——
Jun 13, 2016Slurry Seal Zone APaving & streets——
Jun 13, 2016ADA Access Ramp Improvements, Phase 9Paving & streets——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.