ROWLAND WATER DISTRICT
245 public works projects registered with the California Department of Industrial Relations, 2013–2026 · Rowland Heights, Los Angeles County. Reported contract value: $3,213,759.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 19 | $922,588 |
| 2025 | 23 | $2,168,932 |
| 2024 | 31 | $122,239 |
| 2023 | 17 | — |
| 2022 | 20 | — |
| 2021 | 34 | — |
| 2020 | 23 | — |
| 2019 | 24 | — |
| 2018 | 19 | — |
| 2017 | 17 | — |
| 2016 | 13 | — |
| 2015 | 2 | — |
| 2014 | 1 | — |
| 2013 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Water · 115
- Other · 95
- Parks, landscape & fields · 9
- Buildings & facilities · 9
- Paving & streets · 5
- Electrical, low voltage & AV · 3
- Roofing · 2
- Bridges & structures · 2
- Sewer & wastewater · 2
- Plumbing & restrooms · 1
- Demolition & site work · 1
- Concrete & masonry · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| W A RASIC CONSTRUCTION COMPANY INC | 15 | $235,855 |
| DOTY BROS. EQUIPMENT CO. DBA DOTY BROS. CONSTRUCTION CO. | 8 | $309,722 |
| STUMP FENCE CO | 2 | $413,900 |
| UNIFIED FIELD SERVICES CORPORATION | 1 | $1,383,763 |
| G.M. SAGER CONSTRUCTION CO., INC. | 1 | $171,495 |
| S J LYONS CONSTRUCTION INC | 1 | $141,120 |
| FOOTHILL COMMUNICATIONS INC | 1 | $54,100 |
| J. DE SIGIO CONSTRUCTION, INC. | 1 | $31,300 |
| MC KINNEY CONSTRUCTION COMPANY INC | 1 | $6,297 |
| C & C ENGINEERING | 1 | $6,000 |
| MATT - CHLOR INC | 1 | $2,990 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Sep 23, 2026 | Reservoir 8 RepavingWater | G.M. SAGER CONSTRUCTION CO., INC. | $171,495 |
| Aug 27, 2026 | Install new water serviceWater | — | $11,200 |
| Aug 27, 2026 | New Water Service InstallationWater | — | $7,700 |
| Aug 14, 2026 | New Water ServiceWater | DOTY BROS. EQUIPMENT CO. DBA DOTY BROS. CONSTRUCTION CO. | $3,982 |
| Aug 14, 2026 | New Water ServiceWater | — | $8,115 |
| Aug 14, 2026 | Water Service InstallationWater | — | $9,385 |
| Jul 17, 2026 | Castleton Valve ReplacementOther | — | $26,750 |
| Jul 7, 2026 | New Water ServiceWater | W A RASIC CONSTRUCTION COMPANY INC | $11,867 |
| Jun 2, 2026 | New Water ServicesWater | — | $37,480 |
| May 18, 2026 | Farjardo Meter Vault LidOther | J. DE SIGIO CONSTRUCTION, INC. | $31,300 |
| May 18, 2026 | Meter Vault ReplacementOther | DOTY BROS. EQUIPMENT CO. DBA DOTY BROS. CONSTRUCTION CO. | $37,071 |
| Apr 24, 2026 | New Water ServiceWater | W A RASIC CONSTRUCTION COMPANY INC | $11,324 |
| Apr 22, 2026 | New Service InstallationWater | W A RASIC CONSTRUCTION COMPANY INC | $14,288 |
| Apr 20, 2026 | Water Services InstallationsWater | W A RASIC CONSTRUCTION COMPANY INC | $12,973 |
| Mar 17, 2026 | New Water Service InstallationWater | — | $12,456 |
| Feb 17, 2026 | Joint Line Reservoir FencingWater | STUMP FENCE CO | $357,900 |
| Feb 10, 2026 | Main Office Restroom RemodelPlumbing & restrooms | S J LYONS CONSTRUCTION INC | $141,120 |
| Jan 13, 2026 | Irrigation MeterParks, landscape & fields | MC KINNEY CONSTRUCTION COMPANY INC | $6,297 |
| Jan 12, 2026 | Water Service InstallationWater | — | $9,885 |
| Dec 18, 2025 | ADU Water Service InstallationWater | — | $11,640 |
| Dec 17, 2025 | Radio Communication System UpgradeOther | FOOTHILL COMMUNICATIONS INC | $54,100 |
| Dec 17, 2025 | Water Service InstallationWater | — | $8,345 |
| Nov 24, 2025 | New ADU Water ServiceWater | — | $8,345 |
| Oct 7, 2025 | New ADU Water ServiceWater | — | $8,450 |
| Aug 27, 2025 | ADU Service InstallationWater | DOTY BROS. EQUIPMENT CO. DBA DOTY BROS. CONSTRUCTION CO. | $8,020 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.