Sweetwater Union High School District 2

35 public works projects registered with the California Department of Industrial Relations, 2013–2026 · Chula Vista, San Diego County. Reported contract value: $69,838,100.

Projects by year

YearProjectsReported contract value
20261$2,939,999
20252$16,760,137
20242$44,449,821
20231$5,688,143
20214—
20192—
20185—
20173—
20167—
20142—
20135—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Buildings & facilities · 14
  • Demolition & site work · 5
  • Roofing · 4
  • Electrical, low voltage & AV · 3
  • Design, inspection & consulting · 3
  • Storm drain & flood control · 2
  • Other · 1
  • Painting & flooring · 1
  • Paving & streets · 1
  • Concrete & masonry · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
PLATINUM VISUAL SOLUTIONS1$10,062,457
BEST CONTRACTING SERVICES INC1$2,939,999
UES Professional Solutions 30, LLC1$12,420

Latest projects

DateProjectPrime contractorContract amount
Jul 20, 2026SYH Gym Roof & HVAC ReplacementRoofingBEST CONTRACTING SERVICES INC$2,939,999
Jan 28, 2025RDRM Decommission & Install 3Light PolesDesign, inspection & consultingUES Professional Solutions 30, LLC$12,420
Jan 27, 2025CPH Building & Site ImprovementsDemolition & site work—$16,747,717
May 13, 2024CPH Stadium ModernizationBuildings & facilities—$34,387,364
Mar 11, 2024ELH Library RehabilitationBuildings & facilitiesPLATINUM VISUAL SOLUTIONS$10,062,457
Aug 14, 2023ELH Painting & Flooring ReplacementPainting & flooring—$5,688,143
Sep 20, 2021ORH Marquee RehabilitationOther——
Aug 2, 2021ELH Title IX Softball Facility and ELH TConcrete & masonry——
Jun 11, 2021Hilltop Middle School - 600 Building ModBuildings & facilities——
Apr 28, 2021Otay Ranch T-Mobile and AT&T Cell TowerElectrical, low voltage & AV——
Oct 9, 2019ELH Drop-off/Pick-up ZoneStorm drain & flood control——
Sep 23, 2019CANCELLED - ELH Drop-off/Pick-up Zone -Storm drain & flood control——
Jun 30, 2018MOH/SOH Overhang Assessment RemediationRoofing——
Jun 7, 2018GJH Emergency AbatementDemolition & site work——
Mar 8, 2018CVH - Tennis Court ResurfacingPaving & streets——
Feb 23, 2018Hilltop High School - Tennis Court UpgraDemolition & site work——
Jan 30, 2018CANCELLED - ELH Drop-off/Pick-up ZoneDesign, inspection & consulting——
Jul 7, 2017SOH Title IXBuildings & facilities——
Jun 5, 2017SOH - Portable Classroom ReplacementBuildings & facilities——
May 25, 2017SOH - Portable Classroom ReplacementDesign, inspection & consulting——
Sep 15, 2016SOH Sound System SpeakersBuildings & facilities——
Aug 9, 2016CANCELLED - Hilltop Middle School - 600Demolition & site work——
Jul 12, 2016SOH Portable Mod. - Science Sink InstallBuildings & facilities——
Jun 15, 2016CANCELLED - Hilltop Middle School - ModeBuildings & facilities——
Jun 6, 2016MOM - Roof & Canopies Deferred MaintenanRoofing——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.