23 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Bayside, Humboldt County. Reported contract value: $11,569,905.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 1 | $25,498 |
| 2025 | 4 | $1,845,527 |
| 2024 | 3 | $9,698,880 |
| 2023 | 1 | — |
| 2021 | 1 | — |
| 2020 | 1 | — |
| 2019 | 4 | — |
| 2017 | 4 | — |
| 2016 | 3 | — |
| 2015 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 6
- Design, inspection & consulting · 4
- Other · 3
- Painting & flooring · 3
- Solar, EV & energy · 2
- Demolition & site work · 1
- Paving & streets · 1
- Plumbing & restrooms · 1
- Roofing · 1
- Water · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| NORTH COAST FLOOR & TILE | 2 | $110,913 |
| NEW LIFE VINYL INC DBA NEW LIFE SERVICE CO | 2 | $22,709 |
| ADAMS COMMERCIAL GENERAL CONTRACTING, INC | 1 | $1,737,403 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 22, 2026 | Kitchen, Lounge, Sanzaro FlooringPainting & flooring | NORTH COAST FLOOR & TILE | $25,498 |
| Dec 11, 2025 | MPR FlooringPainting & flooring | NORTH COAST FLOOR & TILE | $85,415 |
| Sep 30, 2025 | Room 11 Water DamageOther | NEW LIFE VINYL INC DBA NEW LIFE SERVICE CO | $9,554 |
| Sep 16, 2025 | Room 12 Water DamageOther | NEW LIFE VINYL INC DBA NEW LIFE SERVICE CO | $13,154 |
| Apr 3, 2025 | JCS and ACGS--Site WorkDemolition & site work | ADAMS COMMERCIAL GENERAL CONTRACTING, INC | $1,737,403 |
| Sep 12, 2024 | AMS PortablesBuildings & facilities | — | $2,361,800 |
| Aug 30, 2024 | Jacoby Creek School Combined (#01-117353Buildings & facilities | — | $3,668,540 |
| Aug 30, 2024 | Jacoby Creek School Combined (#01-117353Buildings & facilities | — | $3,668,540 |
| May 2, 2023 | CalSHAPE Phase 1 HVAC Assessment and MaiDesign, inspection & consulting | — | — |
| Jun 14, 2021 | Jacoby Creek School Underground Water LiWater | — | — |
| Feb 13, 2020 | SHN DTSC PH 1 Addend StudyOther | — | — |
| Aug 15, 2019 | Project One, Contract One, Pave MarkPaving & streets | — | — |
| Jul 30, 2019 | Project One, Contract One fenceBuildings & facilities | — | — |
| Jul 5, 2019 | Project One, Contract One PaintPainting & flooring | — | — |
| Jun 14, 2019 | Project One, Contract OneBuildings & facilities | — | — |
| Aug 7, 2017 | Solar Panels Phase 2Solar, EV & energy | — | — |
| Aug 7, 2017 | Solar PV System Phase 2Design, inspection & consulting | — | — |
| Aug 7, 2017 | Solar PV System Project Phase 2Design, inspection & consulting | — | — |
| Jul 5, 2017 | Classroom Buidling Re-RoofingRoofing | — | — |
| Aug 2, 2016 | FROG and Portable Buildings Fiber OpticsBuildings & facilities | — | — |
| Jun 17, 2016 | Solar PV System ProjectSolar, EV & energy | — | — |
| Jun 17, 2016 | Solar PV System ProjectDesign, inspection & consulting | — | — |
| Jul 2, 2015 | Commercial PlumbingPlumbing & restrooms | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.
Do you bid public works?
Find your license and claim your free Atriam profile. It lists the public works projects registered under your license.
Find my license