41 public works projects registered with the California Department of Industrial Relations, 2012–2026 · Boulder Creek, Santa Cruz County. Reported contract value: $8,366,894.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 1 | $3,524,524 |
| 2025 | 3 | $1,588,790 |
| 2024 | 1 | $3,253,580 |
| 2023 | 5 | — |
| 2022 | 5 | — |
| 2021 | 11 | — |
| 2020 | 5 | — |
| 2019 | 2 | — |
| 2018 | 2 | — |
| 2015 | 1 | — |
| 2014 | 2 | — |
| 2012 | 3 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 15
- Water · 14
- Electrical, low voltage & AV · 3
- Paving & streets · 3
- Parks, landscape & fields · 2
- Bridges & structures · 1
- Demolition & site work · 1
- Painting & flooring · 1
- Storm drain & flood control · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| ANDERSON PACIFIC ENGINEERING CONSTRUCTION INC | 2 | $6,778,104 |
| CORCUS CONSTRUCTION INC | 2 | $1,433,499 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Feb 20, 2026 | DWR Redwood Park & Echo Tank ReplacementParks, landscape & fields | ANDERSON PACIFIC ENGINEERING CONSTRUCTION INC | $3,524,524 |
| Oct 17, 2025 | Highland TankStorm drain & flood control | CORCUS CONSTRUCTION INC | $1,033,099 |
| Jul 18, 2025 | Meter Abandonment and Trench RepairPaving & streets | — | $155,291 |
| Feb 10, 2025 | CA-9 Bridges WMRP Phase IBridges & structures | CORCUS CONSTRUCTION INC | $400,400 |
| Dec 10, 2024 | SLVWD Water System Consolidation Phase 1Water | ANDERSON PACIFIC ENGINEERING CONSTRUCTION INC | $3,253,580 |
| Sep 1, 2023 | 2021 CIP Pipeline ImprovementsOther | — | — |
| Jun 15, 2023 | Fall Creek Fish LadderOther | — | — |
| Jun 7, 2023 | Quail Hollow Road Exploratory RepairPaving & streets | — | — |
| Jun 5, 2023 | Lyon and Big Steel PipelinesOther | — | — |
| Apr 1, 2023 | Redwood Park PipelineParks, landscape & fields | — | — |
| Dec 31, 2022 | HUD Line Emergency BypassOther | — | — |
| May 2, 2022 | Glen Arbor Pipeline ReplacementOther | — | — |
| Feb 28, 2022 | Alta Via Pipeline ReplacementOther | — | — |
| Feb 28, 2022 | Quail Hollow Pipeline ReplacementWater | — | — |
| Jan 23, 2022 | Brookdale Viaduct Pipeline RealignmentOther | — | — |
| Oct 14, 2021 | Huckleberry Island Main RelocationWater | — | — |
| Jul 20, 2021 | Alta Via GeotechOther | — | — |
| Jun 30, 2021 | Alta Via GeotechOther | — | — |
| Jun 30, 2021 | Cross Country Constructability StudyOther | — | — |
| Jun 29, 2021 | Foreman Grading/E.C.Demolition & site work | — | — |
| Jun 29, 2021 | AWIA ERPOther | — | — |
| Jun 14, 2021 | Riverside Grove Booster StationWater | — | — |
| Jun 14, 2021 | Lyon Complex Access Road DesignPaving & streets | — | — |
| Jun 14, 2021 | Blue Ridge Tank GeotechnicalOther | — | — |
| Jun 2, 2021 | Blue Ridge Tank GeotechnicalOther | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.