Jefferson Elementary School District
31 public works projects registered with the California Department of Industrial Relations, 2012–2016 · Daly City.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2016 | 10 | — |
| 2015 | 5 | — |
| 2014 | 8 | — |
| 2013 | 6 | — |
| 2012 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 7
- Painting & flooring · 6
- HVAC & mechanical · 4
- Roofing · 3
- Water · 2
- Electrical, low voltage & AV · 2
- Fire & life safety · 2
- Demolition & site work · 2
- Other · 1
- Concrete & masonry · 1
- Plumbing & restrooms · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 13, 2016 | Colma School Water System UpgradeWater | — | — |
| Jun 13, 2016 | George Washington Heating System UpgradeHVAC & mechanical | — | — |
| Jun 13, 2016 | Daniel Webster Elementary School PaintinPainting & flooring | — | — |
| May 1, 2016 | Main Campus Imnprovements Phas 2B - MechHVAC & mechanical | — | — |
| Apr 11, 2016 | Main Campus Improvements Phase 2B - SiteDemolition & site work | — | — |
| Apr 11, 2016 | Main Campus Improvements Phas 2B - PlumbPlumbing & restrooms | — | — |
| Apr 11, 2016 | Main Campus Improvements Phas 2B - GenerBuildings & facilities | — | — |
| Apr 11, 2016 | Main Campus Improvements Phas 2B - ElectElectrical, low voltage & AV | — | — |
| Apr 11, 2016 | Main Campus Improvements Phas 2B - LandsBuildings & facilities | — | — |
| Apr 11, 2016 | Main Campus Improvements Phas 2B - FireFire & life safety | — | — |
| Jun 11, 2015 | Woodrow Wilson PaintingPainting & flooring | — | — |
| Jun 11, 2015 | Fire Alarm System UpgradeFire & life safety | — | — |
| Jun 11, 2015 | Benjamin Franklin Window Wall ReplacemenBuildings & facilities | — | — |
| Jun 11, 2015 | Westlake Portable Classroom ReplacementBuildings & facilities | — | — |
| May 26, 2015 | Roof Overhang Replacement - DW, FR & TERoofing | — | — |
| Dec 8, 2014 | Structured Cabling UpgradeElectrical, low voltage & AV | — | — |
| Oct 1, 2014 | Thomas R. Pollicita Modernization - PhasBuildings & facilities | — | — |
| Jun 10, 2014 | Westlake Elementary School PaintingPainting & flooring | — | — |
| Jun 10, 2014 | Colma School Roof ReplacementRoofing | — | — |
| Jun 10, 2014 | Marjorie Tobias Elementary School PaintiPainting & flooring | — | — |
| Jun 10, 2014 | George Washington Roof ReplacementRoofing | — | — |
| Jun 10, 2014 | Garden Village Elementary School PaintinPainting & flooring | — | — |
| Apr 28, 2014 | District Office Barrier RemovalOther | — | — |
| Jun 24, 2013 | Covered Walkway Column RepairBuildings & facilities | — | — |
| Jun 10, 2013 | Energy UpgradesHVAC & mechanical | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.