15 public works projects registered with the California Department of Industrial Relations, 2015–2024 · Chico. Reported contract value: $70,000.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2024 | 1 | $70,000 |
| 2021 | 1 | — |
| 2020 | 1 | — |
| 2019 | 2 | — |
| 2017 | 1 | — |
| 2016 | 5 | — |
| 2015 | 4 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 6
- HVAC & mechanical · 3
- Other · 2
- Paving & streets · 1
- Roofing · 1
- Electrical, low voltage & AV · 1
- Fire & life safety · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Apr 24, 2024 | Nord KIT Oven and Hood Install ProjectOther | — | $70,000 |
| Dec 19, 2021 | Basketball Court RepairsPaving & streets | — | — |
| May 28, 2020 | Roof Mount SolarRoofing | — | — |
| Sep 26, 2019 | Swing Set InstallOther | — | — |
| Jul 10, 2019 | HVAC Rooms 13 & 14HVAC & mechanical | — | — |
| Aug 17, 2017 | Fire Alarm Phase 1Fire & life safety | — | — |
| Apr 4, 2016 | Materials TestingBuildings & facilities | — | — |
| Apr 4, 2016 | classroom 13Buildings & facilities | — | — |
| Apr 4, 2016 | classroom 14Buildings & facilities | — | — |
| Jan 31, 2016 | Rooms 13 & 14Buildings & facilities | — | — |
| Jan 31, 2016 | Shade StructureBuildings & facilities | — | — |
| Dec 7, 2015 | Occupancy SensorsBuildings & facilities | — | — |
| Oct 5, 2015 | Nord HVAC upgradeHVAC & mechanical | — | — |
| Aug 10, 2015 | Nord HVAC upgradeHVAC & mechanical | — | — |
| Aug 3, 2015 | Lighting UpgradesElectrical, low voltage & AV | — | — |