Firebaugh Canal Water District
19 public works projects registered with the California Department of Industrial Relations, 2016–2023 · Mendota.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2023 | 6 | — |
| 2022 | 3 | — |
| 2020 | 2 | — |
| 2019 | 1 | — |
| 2018 | 2 | — |
| 2017 | 3 | — |
| 2016 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Solar, EV & energy · 7
- Other · 5
- Buildings & facilities · 4
- Bridges & structures · 3
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Aug 23, 2023 | Solar ProjectSolar, EV & energy | — | — |
| Aug 15, 2023 | Solar ProjectSolar, EV & energy | — | — |
| Aug 4, 2023 | Solar ProjectSolar, EV & energy | — | — |
| Aug 2, 2023 | Solar ProjectSolar, EV & energy | — | — |
| Aug 1, 2023 | Solar ProjectSolar, EV & energy | — | — |
| Apr 1, 2023 | Solar ProjectSolar, EV & energy | — | — |
| Dec 31, 2022 | Solar ProjectSolar, EV & energy | — | — |
| Sep 30, 2022 | 2nd Lift Phase VIOther | — | — |
| Mar 14, 2022 | Office BuildingBuildings & facilities | — | — |
| Nov 17, 2020 | 1st Lift Canal Lining Project Phase IVOther | — | — |
| Oct 5, 2020 | Office DemoBuildings & facilities | — | — |
| May 20, 2019 | 109 StationOther | — | — |
| Nov 5, 2018 | Bullard Weir Jones Weir ModernizationBuildings & facilities | — | — |
| Nov 4, 2018 | Pumping Plant 1 Retaining WallsBridges & structures | — | — |
| Nov 1, 2017 | Pumping Plant 1 Access Retaining WallsBridges & structures | — | — |
| Nov 1, 2017 | Check 1 Modernization ProjectBuildings & facilities | — | — |
| Feb 5, 2017 | 1st Lift Phase 3Other | — | — |
| Dec 19, 2016 | 2nd Lift Canal Lining Project Ph. 4Other | — | — |
| — | Pumping Plant 1 Retaining WallsBridges & structures | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.