59 public works projects registered with the California Department of Industrial Relations, 2015–2026 · King City, Monterey County. Reported contract value: $8,188,396.

Projects by year

YearProjectsReported contract value
20264$2,702,576
20252$3,531,825
20245$1,953,995
20235—
20227—
20217—
20206—
20199—
20186—
20173—
20161—
20151—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Paving & streets · 23
  • Parks, landscape & fields · 13
  • Other · 7
  • Storm drain & flood control · 4
  • Sewer & wastewater · 4
  • Water · 2
  • Electrical, low voltage & AV · 2
  • Bridges & structures · 1
  • Buildings & facilities · 1
  • Solar, EV & energy · 1
  • Roofing · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
KATCH GENERAL AND KATCH2$3,531,825
TEICHERT CONSTRUCTION1$2,379,728
BIG WAKOO FENCE INC1$190,713
MONTEREY PENINSULA ENGINEERING1$73,635
SITEWORX INC1$58,500

Latest projects

DateProjectPrime contractorContract amount
Sep 22, 20262026 Sediment Removal ProjectOtherMONTEREY PENINSULA ENGINEERING$73,635
Apr 22, 2026King City Pool Fencing ProjectParks, landscape & fieldsBIG WAKOO FENCE INC$190,713
Mar 24, 20262025 CDBG Pavement Rehabilitation ProjecPaving & streetsTEICHERT CONSTRUCTION$2,379,728
Feb 24, 2026Fire Station Parking Lot Paving ProjectPaving & streetsSITEWORX INC$58,500
Oct 14, 2025Sewer Replacement ProjectSewer & wastewaterKATCH GENERAL AND KATCH$1,767,201
Oct 14, 2025Sewer Main Replacement ProjectSewer & wastewaterKATCH GENERAL AND KATCH$1,764,624
Oct 23, 20242024 King City Sediment Removal ProjectStorm drain & flood control—$75,995
Sep 11, 20242024 King City Street ProjectPaving & streets—$1,649,000
Jul 9, 2024Tree Trimming Services 2024 & 2025Parks, landscape & fields—$144,000
Jun 17, 2024Miscellaneous Sidewalk Repairs ProjectPaving & streets—$85,000
Mar 3, 2024King City Sidewalk Trip Hazard GrindingPaving & streets——
Oct 17, 20232023 King City Sediment Removal ProjectStorm drain & flood control——
Jul 24, 20232023 Tree Trimming ServicesParks, landscape & fields——
Jun 26, 2023Mesa Del Rey Airport Taxiway A RehabilitPaving & streets——
Jun 12, 2023King City Downtown PlazaParks, landscape & fields——
May 19, 2023King City Downtown Streetscape PlanOther——
Nov 14, 20222022 King City Sewer ImprovementsSewer & wastewater——
Oct 13, 20222022 King City Sediment Removal ProjectStorm drain & flood control——
Oct 3, 20222022 King City Street ProjectPaving & streets——
Oct 1, 20222022 Citywide Street Re-Striping ProjectPaving & streets——
Sep 19, 2022Bus Stop Improvements for KC Fixed RoutePaving & streets——
Jul 14, 2022King City Waste Water Treatment Plant DeWater——
Feb 6, 2022Forden Park Playground Rubberized SurfacParks, landscape & fields——
Nov 1, 20212021 King City Sediment Removal ProjectOther——
Sep 27, 2021City Park 2 to 5 Playground Rubberized SParks, landscape & fields——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.