King City
59 public works projects registered with the California Department of Industrial Relations, 2015–2026 · King City, Monterey County. Reported contract value: $8,188,396.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 4 | $2,702,576 |
| 2025 | 2 | $3,531,825 |
| 2024 | 5 | $1,953,995 |
| 2023 | 5 | — |
| 2022 | 7 | — |
| 2021 | 7 | — |
| 2020 | 6 | — |
| 2019 | 9 | — |
| 2018 | 6 | — |
| 2017 | 3 | — |
| 2016 | 1 | — |
| 2015 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Paving & streets · 23
- Parks, landscape & fields · 13
- Other · 7
- Storm drain & flood control · 4
- Sewer & wastewater · 4
- Water · 2
- Electrical, low voltage & AV · 2
- Bridges & structures · 1
- Buildings & facilities · 1
- Solar, EV & energy · 1
- Roofing · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| KATCH GENERAL AND KATCH | 2 | $3,531,825 |
| TEICHERT CONSTRUCTION | 1 | $2,379,728 |
| BIG WAKOO FENCE INC | 1 | $190,713 |
| MONTEREY PENINSULA ENGINEERING | 1 | $73,635 |
| SITEWORX INC | 1 | $58,500 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Sep 22, 2026 | 2026 Sediment Removal ProjectOther | MONTEREY PENINSULA ENGINEERING | $73,635 |
| Apr 22, 2026 | King City Pool Fencing ProjectParks, landscape & fields | BIG WAKOO FENCE INC | $190,713 |
| Mar 24, 2026 | 2025 CDBG Pavement Rehabilitation ProjecPaving & streets | TEICHERT CONSTRUCTION | $2,379,728 |
| Feb 24, 2026 | Fire Station Parking Lot Paving ProjectPaving & streets | SITEWORX INC | $58,500 |
| Oct 14, 2025 | Sewer Replacement ProjectSewer & wastewater | KATCH GENERAL AND KATCH | $1,767,201 |
| Oct 14, 2025 | Sewer Main Replacement ProjectSewer & wastewater | KATCH GENERAL AND KATCH | $1,764,624 |
| Oct 23, 2024 | 2024 King City Sediment Removal ProjectStorm drain & flood control | — | $75,995 |
| Sep 11, 2024 | 2024 King City Street ProjectPaving & streets | — | $1,649,000 |
| Jul 9, 2024 | Tree Trimming Services 2024 & 2025Parks, landscape & fields | — | $144,000 |
| Jun 17, 2024 | Miscellaneous Sidewalk Repairs ProjectPaving & streets | — | $85,000 |
| Mar 3, 2024 | King City Sidewalk Trip Hazard GrindingPaving & streets | — | — |
| Oct 17, 2023 | 2023 King City Sediment Removal ProjectStorm drain & flood control | — | — |
| Jul 24, 2023 | 2023 Tree Trimming ServicesParks, landscape & fields | — | — |
| Jun 26, 2023 | Mesa Del Rey Airport Taxiway A RehabilitPaving & streets | — | — |
| Jun 12, 2023 | King City Downtown PlazaParks, landscape & fields | — | — |
| May 19, 2023 | King City Downtown Streetscape PlanOther | — | — |
| Nov 14, 2022 | 2022 King City Sewer ImprovementsSewer & wastewater | — | — |
| Oct 13, 2022 | 2022 King City Sediment Removal ProjectStorm drain & flood control | — | — |
| Oct 3, 2022 | 2022 King City Street ProjectPaving & streets | — | — |
| Oct 1, 2022 | 2022 Citywide Street Re-Striping ProjectPaving & streets | — | — |
| Sep 19, 2022 | Bus Stop Improvements for KC Fixed RoutePaving & streets | — | — |
| Jul 14, 2022 | King City Waste Water Treatment Plant DeWater | — | — |
| Feb 6, 2022 | Forden Park Playground Rubberized SurfacParks, landscape & fields | — | — |
| Nov 1, 2021 | 2021 King City Sediment Removal ProjectOther | — | — |
| Sep 27, 2021 | City Park 2 to 5 Playground Rubberized SParks, landscape & fields | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.