106 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Los Altos, San Mateo County. Reported contract value: $15,053,409.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 16 | $7,665,887 |
| 2025 | 9 | $2,512,842 |
| 2024 | 6 | $4,874,680 |
| 2023 | 14 | — |
| 2022 | 5 | — |
| 2021 | 10 | — |
| 2020 | 2 | — |
| 2019 | 11 | — |
| 2018 | 8 | — |
| 2017 | 9 | — |
| 2016 | 7 | — |
| 2015 | 7 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 32
- Demolition & site work · 16
- Buildings & facilities · 13
- Parks, landscape & fields · 12
- Storm drain & flood control · 7
- Paving & streets · 5
- Bridges & structures · 5
- Water · 3
- Roofing · 3
- Painting & flooring · 2
- Plumbing & restrooms · 2
- Electrical, low voltage & AV · 2
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| ECOLOGICAL CONCERNS INCORPORATED | 2 | $2,308,747 |
| SAE CONSULTING ENGINEERING | 2 | $880,500 |
| RANDAZZO ENTERPRISES INC | 2 | $762,453 |
| SFT CONSTRUCTION CORP | 2 | $484,000 |
| JOSEPH J ALBANESE INC | 1 | $2,417,746 |
| SOUTHWEST FENCE AND SUPPLY | 1 | $359,725 |
| Biggs Cardosa Associates, Inc. | 1 | $249,799 |
| IRISH EXCAVATION | 1 | $222,222 |
| ROCHA CONSTRUCTION & EARTHWORKS INC | 1 | $184,000 |
| TOP LINE ENGINEERS INC | 1 | $158,002 |
| SILICON VALLEY PAVING INC | 1 | $139,494 |
| ALTOR CONSTRUCTION LLC | 1 | $138,840 |
| Old La Honda General Engineering | 1 | $119,679 |
| ECAST ENGINEERING INC | 1 | $90,865 |
| PRIMAL PAINT INC | 1 | $60,630 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Aug 27, 2026 | KMM Ecosystem ResiliencyParks, landscape & fields | Forster & Kroeger Landscape Maintenance, Inc. | $346,135 |
| Aug 26, 2026 | Johnston Ranch Water Distribution Proj.Other | TOP LINE ENGINEERS INC | $158,002 |
| Aug 12, 2026 | L'Andre and Big Dipper Barn RemovalOther | RANDAZZO ENTERPRISES INC | $275,304 |
| Aug 12, 2026 | Natural Lands Master Weed ProjectOther | ECOLOGICAL CONCERNS INCORPORATED | $1,846,005 |
| Aug 12, 2026 | Hawthorns Reroofing ProjectOther | SAE CONSULTING ENGINEERING | $720,000 |
| Aug 12, 2026 | Purisima Pond RestorationTraffic & signals | Old La Honda General Engineering | $119,679 |
| Jul 8, 2026 | Purisima UplandOther | RANDAZZO ENTERPRISES INC | $487,149 |
| Jun 15, 2026 | Bear Creek Stables Arena Repair ProjectOther | R & M PAVING CONTRACTORS, INC. | $41,571 |
| Jun 10, 2026 | Driveway Repairs at Incerpi and CuhnaOther | SILICON VALLEY PAVING INC | $139,494 |
| Apr 22, 2026 | Bear Creek Redwoods North Parking AreaPaving & streets | JOSEPH J ALBANESE INC | $2,417,746 |
| Apr 22, 2026 | Miramontes Crossing ReplacementBridges & structures | Biggs Cardosa Associates, Inc. | $249,799 |
| Apr 8, 2026 | Fremont Older Historic House Re-RoofingRoofing | SAE CONSULTING ENGINEERING | $160,500 |
| Mar 25, 2026 | Foothill Field Office Foundation RepairDesign, inspection & consulting | NEIL O ANDERSON AND ASSOCIATES INC | $12,056 |
| Mar 11, 2026 | Conservation Grazing Master WeedOther | ECOLOGICAL CONCERNS INCORPORATED | $462,742 |
| Mar 11, 2026 | Foothill Field Office Foundation RepairParks, landscape & fields | ALTOR CONSTRUCTION LLC | $138,840 |
| Jan 28, 2026 | LHC Agricultural Water DevelopmentWater | ECAST ENGINEERING INC | $90,865 |
| Sep 10, 2025 | Ravenswood Pedestrian GateStorm drain & flood control | ROEBBELEN CONTRACTING INC | $95,360 |
| Aug 20, 2025 | Wildlife-friendly fencing on CG UnitsBuildings & facilities | SOUTHWEST FENCE AND SUPPLY | $359,725 |
| Jul 23, 2025 | South Area Demolition ProjectDemolition & site work | — | $713,917 |
| Jul 9, 2025 | Lone Madrone Corral Replacement ProjectOther | SFT CONSTRUCTION CORP | $295,000 |
| Jul 9, 2025 | Madonna Creek Dam Repair ProjectBuildings & facilities | ROCHA CONSTRUCTION & EARTHWORKS INC | $184,000 |
| Jul 9, 2025 | Prospect Road Culvert ReplacementStorm drain & flood control | IRISH EXCAVATION | $222,222 |
| Apr 23, 2025 | Bathtub Loop Drainage Upgrade ProjectStorm drain & flood control | HALF MOON BAY GRADING & PAVING INC | $392,987 |
| Apr 23, 2025 | Hawthorns Stabilization & Debris RemovalOther | SFT CONSTRUCTION CORP | $189,000 |
| Jan 23, 2025 | Paint 3 Residences, 2 acc structuresPainting & flooring | PRIMAL PAINT INC | $60,630 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.