Fair Oaks Water District
23 public works projects registered with the California Department of Industrial Relations, 2016–2026 · Fair Oaks, Sacramento County. Reported contract value: $8,250,176.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 2 | $1,071,299 |
| 2025 | 3 | $7,178,877 |
| 2024 | 1 | — |
| 2023 | 1 | — |
| 2022 | 4 | — |
| 2021 | 1 | — |
| 2020 | 5 | — |
| 2019 | 2 | — |
| 2017 | 1 | — |
| 2016 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Water · 11
- Other · 8
- Paving & streets · 2
- Traffic & signals · 1
- Painting & flooring · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| T & S CONSTRUCTION CO INC DBA THOMAS B SPINELLA CONSTRUCTION | 1 | $3,115,000 |
| NOR-CAL PUMP & WELL DRILLING, INC. | 1 | $1,176,776 |
| ARB INC | 1 | $927,622 |
| GHILOTTI CONSTRUCTION COMPANY INC | 1 | $143,677 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 15, 2026 | New York Avenue Main Phase IIOther | ARB INC | $927,622 |
| Apr 2, 2026 | County OverlayPaving & streets | GHILOTTI CONSTRUCTION COMPANY INC | $143,677 |
| Oct 20, 2025 | New York Well Phase II - Well EquippingWater | T & S CONSTRUCTION CO INC DBA THOMAS B SPINELLA CONSTRUCTION | $3,115,000 |
| May 12, 2025 | T-Main Replacement Phases I & IIOther | — | $2,887,101 |
| Mar 12, 2025 | Northridge Well #15 Production WellWater | NOR-CAL PUMP & WELL DRILLING, INC. | $1,176,776 |
| May 23, 2024 | New York Ave - Phase IWater | — | — |
| Jul 10, 2023 | Water Facility Improvements on Hazel AvePaving & streets | — | — |
| Nov 20, 2022 | Exterior Power Wash & PaintingPainting & flooring | — | — |
| Jun 13, 2022 | Relocate Main at California Ave & TemescOther | — | — |
| Apr 25, 2022 | Sac Overlay SB1 2021Traffic & signals | — | — |
| Jan 8, 2022 | Skyway Well Phase 2 Construction, SkywayWater | — | — |
| Oct 25, 2021 | Geotechnical Investigation - Corp YardOther | — | — |
| Dec 19, 2020 | Replacement of approximately 300 LF of wWater | — | — |
| Oct 12, 2020 | Replacement of approximately 400 LF of wWater | — | — |
| Oct 12, 2020 | Replacement of 550 LF of 12in water mainWater | — | — |
| Jun 15, 2020 | Skyway Well # 14Water | — | — |
| Jun 15, 2020 | New York Well # 13Water | — | — |
| Jun 4, 2019 | Skyway Tank Site Test HoleOther | — | — |
| Apr 30, 2019 | Main Replacement Hazel AvenueOther | — | — |
| Jan 1, 2017 | 24-Inch Transmission Water mainWater | — | — |
| Oct 10, 2016 | Pump Inspection and Repair Northridge WeOther | — | — |
| Apr 14, 2016 | Madison Well - Design/Equip/EtcWater | — | — |
| — | Relocate Main at California Ave & TemescOther | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.