COUNTY SANITATION DISTRICTS OF LOS ANGELES COUNTY
148 public works projects registered with the California Department of Industrial Relations, 2010–2024 · Whittier.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2024 | 1 | — |
| 2023 | 2 | — |
| 2022 | 7 | — |
| 2021 | 27 | — |
| 2020 | 26 | — |
| 2019 | 24 | — |
| 2018 | 28 | — |
| 2017 | 24 | — |
| 2016 | 6 | — |
| 2012 | 1 | — |
| 2010 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Sewer & wastewater · 66
- Other · 22
- Demolition & site work · 18
- Electrical, low voltage & AV · 11
- Paving & streets · 7
- Buildings & facilities · 6
- Concrete & masonry · 6
- Water · 4
- HVAC & mechanical · 2
- Storm drain & flood control · 2
- Bridges & structures · 1
- Fire & life safety · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Mar 13, 2024 | Gramercy Place Trunk Pavement Repair inPaving & streets | — | — |
| Nov 18, 2023 | Emergency Repair of the JO B Unit 2B TruSewer & wastewater | — | — |
| Feb 27, 2023 | COMPTON FIELD OFFICE REMODELParks, landscape & fields | — | — |
| Dec 21, 2022 | D22 Main Relief Trunk Sewer Between MH 2Sewer & wastewater | — | — |
| Nov 26, 2022 | Los Coyotes Diagonal Trunk Lateral RepaiOther | — | — |
| Nov 19, 2022 | District 17 Main Trunk Between MH 17 001Other | — | — |
| Nov 12, 2022 | INSTALL VERKADA SECURITY CAMERAS AT SHOEElectrical, low voltage & AV | — | — |
| Oct 24, 2022 | Gardena Pumping Plant Facility ReplacemeBuildings & facilities | — | — |
| Jan 30, 2022 | Joint Outfall C Unit 6G Trunk Sewer RehaSewer & wastewater | — | — |
| Jan 18, 2022 | District 5 Interceptor Sewer RehabilitatSewer & wastewater | — | — |
| Dec 7, 2021 | Marina Pumping Plant No. 02Demolition & site work | — | — |
| Nov 30, 2021 | South Whittier Outfall Relief Trunk SeweSewer & wastewater | — | — |
| Nov 8, 2021 | Scholl Canyon Landfill Storm Water ManagStorm drain & flood control | — | — |
| Nov 7, 2021 | Joint Outfall C Unit 1 Force Main RehabiOther | — | — |
| Nov 3, 2021 | San Jose Creek Water Reclamation Plant ROther | — | — |
| Oct 12, 2021 | Joint Administration Office Power ServicElectrical, low voltage & AV | — | — |
| Oct 4, 2021 | District 14 Trunk Sewer A Between MH 14-Sewer & wastewater | — | — |
| Oct 1, 2021 | San Marino Outfall Trunk Sewer RehabilitSewer & wastewater | — | — |
| Oct 1, 2021 | Bullis Road-Temple Street Trunk Sewer ReSewer & wastewater | — | — |
| Oct 1, 2021 | District 2 Interceptor Trunk Sewer RehabSewer & wastewater | — | — |
| Sep 20, 2021 | Downey Ave Extension Trunk between manhoSewer & wastewater | — | — |
| Sep 10, 2021 | North Long Beach Relief Trunk Sewer RehaSewer & wastewater | — | — |
| Aug 23, 2021 | South Bay Cities Main Trunk Sewer RehabiSewer & wastewater | — | — |
| Aug 14, 2021 | Joint Outfall B Unit 8H Emergency PointOther | — | — |
| Aug 1, 2021 | Saugus WRP Power Distribution System ModBuildings & facilities | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.
Do you bid public works?