Merced County Regional Waste Authority

38 public works projects registered with the California Department of Industrial Relations, 2016–2026 · Merced, Merced County. Reported contract value: $8,617,244.

Projects by year

YearProjectsReported contract value
20262$483,973
20252$8,133,271
20242—
20236—
20226—
20211—
20202—
20198—
20184—
20172—
20162—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 18
  • Buildings & facilities · 8
  • Water · 6
  • Painting & flooring · 3
  • Electrical, low voltage & AV · 2
  • Paving & streets · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
BLUE FLAME CREW WEST LLC1$435,201
CALIFORNIA BUILDING STRUCTURES INC1$293,973
STEARNS CONRAD AND SCHMIDT CONSULTING ENGINEERS INC1$190,000

Latest projects

DateProjectPrime contractorContract amount
Sep 17, 2026Surveillance Improvement and MaintenanceBuildings & facilitiesCALIFORNIA BUILDING STRUCTURES INC$293,973
May 28, 20262026 LFGCCS Fire Repair - H59OtherSTEARNS CONRAD AND SCHMIDT CONSULTING ENGINEERS INC$190,000
Sep 19, 20252025 GCCS Improvements for P6 @H59 LFWaterBLUE FLAME CREW WEST LLC$435,201
Feb 20, 2025BW Phase 3A and Surface ImpoundmentOther—$7,698,070
May 20, 2024H59 Probe 45 Soil Boring EvaluationOther——
Mar 25, 2024Highway 59 Landfill Improvements ProjectOther——
Oct 30, 2023Hwy 59 GW Monitoring Well RelocationWater——
Oct 30, 2023Billy Wright Landfill LCRS Power SystemElectrical, low voltage & AV——
Oct 16, 2023Highway 59 Landfill Facility ImprovementBuildings & facilities——
Oct 16, 2023Highway 59 Landfill Facility ImprovementBuildings & facilities——
Jul 24, 2023Highway 59 Landfill 2023 Gas CollectionOther——
Jun 5, 2023Highway 59 Landfill Flare Station ImprovOther——
May 9, 2022Highway 59 Phase 6B-2 Landfill Liner ExpOther——
Apr 18, 2022TestOther——
Apr 11, 2022Billy Wright Phase 2C Landfill Liner ExpOther——
Feb 17, 20222022 Pump and Treat ReplacementWater——
Jan 10, 2022Hwy 59 Exterior Light Repair/UpgradeBuildings & facilities——
Jan 4, 2022Hwy 59 Scalehouse Interior Light UpgradeBuildings & facilities——
May 24, 2021Billy Wright Landfill Entrance FacilityBuildings & facilities——
Sep 18, 2020Flare Painting 2020Painting & flooring——
Jun 15, 2020Highway 59 Landfill Scale AdditionBuildings & facilities——
Dec 18, 2019Ongoing Communications MaintenanceOther——
Nov 4, 2019Tire Wash UpgradeOther——
Nov 3, 2019Network ConnectionElectrical, low voltage & AV——
Oct 31, 2019Fuel Tank Painting 2019 - 2Painting & flooring——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.