252 public works projects registered with the California Department of Industrial Relations, 2015–2026 · San Rafael, Marin County. Reported contract value: $20,108,316.

Projects by year

YearProjectsReported contract value
202614$3,377,724
202512$4,236,720
202425$11,295,518
202318$200,000
202224—
202113—
202014—
201913—
201823—
201757—
201613—
201514—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Paving & streets · 60
  • Other · 40
  • Buildings & facilities · 30
  • Storm drain & flood control · 29
  • Traffic & signals · 21
  • Parks, landscape & fields · 18
  • Electrical, low voltage & AV · 10
  • Painting & flooring · 8
  • Water · 6
  • Bridges & structures · 6
  • HVAC & mechanical · 5
  • Plumbing & restrooms · 5

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
MICHAEL PAUL COMPANY INC5$646,801
PRECISION CONCRETE CUTTING4$263,399
MATRIX HG INC4$256,519
AMERICAN ASPHALT REPAIR AND RESURFACING COMPANY INC2$1,820,682
MIKE BROWN ELECTRIC CO2$779,235
BAYSIDE STRIPE & SEAL INC2$177,514
CHRISP COMPANY2$83,865
SPYE CONSERVATION INCORPORATED2$82,000
ABLE FENCE COMPANY, INC.2$67,131
RAPID SERVICES LLC DBA RAPID GRADING SERVICES1$804,950
AVI-SPL LLC1$221,131
ROSS RECREATION EQUIPMENT COMPANY INC1$85,545
D C ELECTRIC GROUP INC1$51,850
R & S ERECTION OF RICHMOND INC1$40,000
Bay Alarm Company1$1,700

Latest projects

DateProjectPrime contractorContract amount
Aug 30, 2026Deer Valley Prescribed Pile Burn ProjectOtherSPYE CONSERVATION INCORPORATED$42,000
Jul 20, 2026Digout Project (Phase 1) Point San PedroTraffic & signalsAMERICAN ASPHALT REPAIR AND RESURFACING COMPANY INC$910,341
Jul 20, 20262025 Pavement Management Program PavingTraffic & signalsAMERICAN ASPHALT REPAIR AND RESURFACING COMPANY INC$910,341
Jul 1, 2026Citywide Quarterly HVAC MaintenanceHVAC & mechanicalMATRIX HG INC$175,000
Jun 29, 2026Digout Project (Phase 1) Point San PedroTraffic & signalsMICHAEL PAUL COMPANY INC$175,159
Jun 8, 2026Civic Center Dr Bikeway StripingPaving & streetsBAYSIDE STRIPE & SEAL INC$161,058
Jun 8, 2026Sidewalk Shaving - Phase 3 FY26Paving & streetsPRECISION CONCRETE CUTTING$128,000
May 18, 2026DPW Kempower InstallationOtherEVCHARGE4U INC$32,404
May 18, 2026Large Trash Capture: SR-129 and SR-143WaterCORCUS CONSTRUCTION INC$363,850
Apr 20, 2026620 Canal Street FencingPaving & streetsABLE FENCE COMPANY, INC.$37,263
Apr 13, 2026EVSE Installation - ElectricalSolar, EV & energyMIKE BROWN ELECTRIC CO$263,235
Mar 17, 2026DPW EVSE InstallationSolar, EV & energyMICHAEL PAUL COMPANY INC$99,073
Mar 9, 2026Fire Station 54 App Bay Door ReplacementBuildings & facilitiesR & S ERECTION OF RICHMOND INC$40,000
Feb 5, 2026San Rafael Hill Prescribed Pile BurnOtherSPYE CONSERVATION INCORPORATED$40,000
Dec 15, 2025Lincoln Ave Corridor Safety ImprovementsTraffic & signalsALTOR CONSTRUCTION LLC$284,480
Nov 13, 2025Falkirk Alarm Panel UpgradeOtherBay Alarm Company$1,700
Sep 24, 2025Fremont & Marquard CMP ReplacementOtherMICHAEL PAUL COMPANY INC$25,995
Sep 11, 2025Replacement of Two Compressors @ PSCBuildings & facilitiesMATRIX HG INC$41,541
Sep 9, 2025PSC Evidence Locker FencingBuildings & facilitiesABLE FENCE COMPANY, INC.$29,868
Sep 2, 2025Pickleweed Library RenovationBuildings & facilitiesARNTZ BUILDERS INC$1,984,974
Jul 21, 2025Council Chambers Audio-Video UpgradesElectrical, low voltage & AVAVI-SPL LLC$221,131
May 19, 2025FY25 CMP Replacement Materials TestingPaving & streets—$12,758
May 9, 2025Mahon Creek Path Bike RerouteOtherCHRISP COMPANY$23,665
Mar 17, 2025Canal Neighborhood Active TransportationOtherBKF ENGINEERS$1,264,034
Feb 24, 2025Fremont/Marquard Ave Minor Conc. RepairConcrete & masonryMICHAEL PAUL COMPANY INC$195,000

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.