City of Orinda
82 public works projects registered with the California Department of Industrial Relations, 2015–2024 · Orinda.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2024 | 9 | — |
| 2023 | 20 | — |
| 2022 | 7 | — |
| 2021 | 8 | — |
| 2020 | 5 | — |
| 2019 | 8 | — |
| 2018 | 5 | — |
| 2017 | 4 | — |
| 2016 | 5 | — |
| 2015 | 8 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 18
- Paving & streets · 18
- Storm drain & flood control · 17
- Bridges & structures · 7
- Parks, landscape & fields · 7
- Traffic & signals · 4
- HVAC & mechanical · 3
- Sewer & wastewater · 3
- Electrical, low voltage & AV · 2
- Buildings & facilities · 1
- Demolition & site work · 1
- Roofing · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jul 1, 2024 | Group 2 Stormdrain liningStorm drain & flood control | — | — |
| Jun 24, 2024 | Install pipe liner on GloriettaOther | — | — |
| Jun 18, 2024 | ree and fire clearance on Camino PabloOther | — | — |
| Jun 3, 2024 | 2023 Annual Storm Drain Repair Project CStorm drain & flood control | — | — |
| Jun 3, 2024 | San Pablo Creek Culvert Repair ProjectStorm drain & flood control | — | — |
| Jun 1, 2024 | Cam. Sobrante retaining wallBridges & structures | — | — |
| May 20, 2024 | Repave bridge approach Bear Creek RdBridges & structures | — | — |
| May 20, 2024 | Repave-regrade Moraga Rd near Cam. Enc.Paving & streets | — | — |
| May 10, 2024 | Potholes on Oak RdPaving & streets | — | — |
| Dec 31, 2023 | Library Boiler replacementHVAC & mechanical | — | — |
| Dec 18, 2023 | MORAGA WAY & VALLEY VIEW DRIVE RRFB CROSOther | — | — |
| Dec 4, 2023 | Glorietta Embankment RepairOther | — | — |
| Nov 27, 2023 | El Toyonal Emergency RepairOther | — | — |
| Nov 19, 2023 | Kindergym HVAC replacementHVAC & mechanical | — | — |
| Nov 5, 2023 | Tarry Lane Emergency RepairOther | — | — |
| Oct 30, 2023 | Install pipe liner Sleepy Hollow Ln., neOther | — | — |
| Oct 30, 2023 | Install pipe liner adjacent to 6 DonaldOther | — | — |
| Oct 18, 2023 | Install pipe liner Bobolink Rd., near #4Other | — | — |
| Oct 12, 2023 | Install pipe liner adjacent to 90 Tara ROther | — | — |
| Sep 7, 2023 | 2023 Pavement RehabilitationPaving & streets | — | — |
| Sep 1, 2023 | 2023 Annual Pavement Rehabilitation ProjStorm drain & flood control | — | — |
| Aug 14, 2023 | Tennis Court Lighting RetrofitElectrical, low voltage & AV | — | — |
| Jul 13, 2023 | Canon Embankment StabilizationOther | — | — |
| Jul 11, 2023 | Red Flag parking Sign ProjecectOther | — | — |
| Jul 5, 2023 | Group 1 Stormdrain Lining ProjectStorm drain & flood control | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.
Do you bid public works?
Find your license and claim your free Atriam profile. It lists the public works projects registered under your license.
Find my license