City of Sacramento Department of Utilities
122 public works projects registered with the California Department of Industrial Relations, 2017–2026 · Sacramento. Reported contract value: $54,210,327.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 15 | $30,652,282 |
| 2025 | 9 | $15,087,173 |
| 2024 | 10 | $2,838,722 |
| 2023 | 7 | $114,759 |
| 2022 | 4 | — |
| 2021 | 15 | — |
| 2020 | 15 | — |
| 2019 | 12 | — |
| 2018 | 19 | — |
| 2017 | 9 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Sewer & wastewater · 52
- Water · 35
- Other · 17
- Storm drain & flood control · 7
- Electrical, low voltage & AV · 4
- Design, inspection & consulting · 3
- Buildings & facilities · 2
- Bridges & structures · 1
- Paving & streets · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| SORACCO INC | 3 | $5,633,588 |
| STEVE P. RADOS, INC. | 2 | $5,583,470 |
| Wood Rodgers Inc | 2 | $1,520,542 |
| CLYDE G STEAGALL INC | 2 | $1,256,628 |
| PISOR FENCE DIVISION INC | 2 | $1,063,794 |
| Azuria Water Solutions, Inc. | 1 | $16,966,203 |
| FARR CONSTRUCTION CORPORATION | 1 | $4,609,600 |
| SHIMMICK CONSTRUCTION COMPANY INC | 1 | $2,750,000 |
| ARB INC | 1 | $2,141,141 |
| NMI Industrial Holdings, LLC | 1 | $1,215,200 |
| BARAN ELECTRIC | 1 | $949,280 |
| PACIFIC COAST CONSTRUCTION SVC INC | 1 | $880,000 |
| KLEINFELDER INC | 1 | $598,450 |
| BKF ENGINEERS | 1 | $566,505 |
| GRAVITY CONSTRUCTION | 1 | $541,642 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Sep 3, 2026 | Westlake Sluice Gate Replacement ProjectOther | CLYDE G STEAGALL INC | $258,965 |
| Aug 5, 2026 | Basin 111 Mahole Installation ProjectDesign, inspection & consulting | NV5, INC. | $36,324 |
| Jul 31, 2026 | Arden Way CMP Storm Drains ReplacementSewer & wastewater | GRAVITY CONSTRUCTION | $541,642 |
| Jul 10, 2026 | North 5th St Parallel Storm Trunk MainSewer & wastewater | STEVE P. RADOS, INC. | $2,791,735 |
| Jun 3, 2026 | Facility Chemical Containment CoatingSewer & wastewater | MASON PAINTING INC | $371,000 |
| Jun 3, 2026 | Basin 111 Manhole Installation ProjectSewer & wastewater | ACE-HIGH ENGINEERING | $180,894 |
| May 18, 2026 | City College Reservoir Transmission MainWater | BKF ENGINEERS | $566,505 |
| May 13, 2026 | Richards Blvd Drainage ImprovementsSewer & wastewater | ARB INC | $2,141,141 |
| Apr 3, 2026 | St Luke's Detention BasinStorm drain & flood control | PACIFIC COAST CONSTRUCTION SVC INC | $880,000 |
| Apr 2, 2026 | Sump 157 Security ImprovementsSewer & wastewater | PISOR FENCE DIVISION INC | $531,897 |
| Mar 26, 2026 | N 5th Street Parallel Storm Trunk MainStorm drain & flood control | STEVE P. RADOS, INC. | $2,791,735 |
| Mar 11, 2026 | Sump 117 Electrical ImprovementsSewer & wastewater | CLYDE G STEAGALL INC | $997,663 |
| Feb 25, 2026 | Del Rio Sewer Force Main RehabilitationSewer & wastewater | Azuria Water Solutions, Inc. | $16,966,203 |
| Feb 25, 2026 | Pocket Road Sewer Replacement East ShoreSewer & wastewater | SUBTERRA CONSTRUCTION INC | $457,600 |
| Feb 25, 2026 | Lower Beach Lake Berm Seepage MitigationOther | SORACCO INC | $1,138,978 |
| Dec 24, 2025 | Dooley Field Electrical RehabElectrical, low voltage & AV | TRUE BLUE AUTOMATION SERVICES | $217,500 |
| Nov 7, 2025 | Eleanor Ave Storm Drain ModificationSewer & wastewater | CENTRAL VALLEY ENGINEERING & ASPHALT INC | $171,969 |
| Jul 30, 2025 | Meadowview Communication TowerOther | — | $233,372 |
| Jul 17, 2025 | Sump 89 Outfall Replacement ProjectSewer & wastewater | SHIMMICK CONSTRUCTION COMPANY INC | $2,750,000 |
| May 27, 2025 | CSS Pipe Program R&R Block 6Sewer & wastewater | SORACCO INC | $1,186,368 |
| May 27, 2025 | Del Paso Infrastructure NeedsSewer & wastewater | SORACCO INC | $3,308,242 |
| Apr 9, 2025 | Pioneer Structural RepairsWater | NMI Industrial Holdings, LLC | $1,215,200 |
| Jan 20, 2025 | Medical Center Reservoir RehabilitationWater | FARR CONSTRUCTION CORPORATION | $4,609,600 |
| Jan 8, 2025 | Well Site FeasibilityWater | Wood Rodgers Inc | $1,394,922 |
| Oct 9, 2024 | CSS Pipe Program Block 5 R&RSewer & wastewater | — | $687,688 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.
Do you bid public works?
Find your license and claim your free Atriam profile. It lists the public works projects registered under your license.
Find my license