113 public works projects registered with the California Department of Industrial Relations, 2013–2024 · Edison.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2024 | 9 | — |
| 2023 | 16 | — |
| 2022 | 4 | — |
| 2021 | 2 | — |
| 2020 | 8 | — |
| 2019 | 1 | — |
| 2018 | 1 | — |
| 2017 | 4 | — |
| 2016 | 32 | — |
| 2015 | 19 | — |
| 2014 | 4 | — |
| 2013 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 40
- Buildings & facilities · 25
- Parks, landscape & fields · 19
- Paving & streets · 7
- Painting & flooring · 6
- Concrete & masonry · 4
- Electrical, low voltage & AV · 3
- Plumbing & restrooms · 3
- Demolition & site work · 2
- Roofing · 2
- Sewer & wastewater · 1
- HVAC & mechanical · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Aug 28, 2024 | Kinder Shade StructureBuildings & facilities | — | — |
| Jun 12, 2024 | Edison Auditorium FloorsOther | — | — |
| Jun 10, 2024 | Edison Auditorium FloorsOther | — | — |
| Jun 10, 2024 | Orangewood Elementary Parking AreaOther | — | — |
| Jun 10, 2024 | Edison Middle School Parking AreaBuildings & facilities | — | — |
| Jun 3, 2024 | Orangewood Exterior RepaintingPainting & flooring | — | — |
| Jun 3, 2024 | Edison Middle School Exterior RepaintingPainting & flooring | — | — |
| May 1, 2024 | 4 T-K Classrooms-Orangewood ES-playgrounParks, landscape & fields | — | — |
| Apr 15, 2024 | Orangewood PlaygroundParks, landscape & fields | — | — |
| Dec 18, 2023 | Kinder play structureParks, landscape & fields | — | — |
| Oct 2, 2023 | ESD - MOT Metal BuildingBuildings & facilities | — | — |
| Aug 21, 2023 | 4 T-K Classrooms-Orangewood ES-02-16-000Paving & streets | — | — |
| Aug 8, 2023 | 4 T-K Classrooms-Orangewood ES-TIBuildings & facilities | — | — |
| Jul 26, 2023 | Edison AdminOther | — | — |
| Jul 24, 2023 | 4 T-K Classrooms-Orangewood ES-02-15-000Concrete & masonry | — | — |
| Jul 24, 2023 | Edison Parking lotOther | — | — |
| Jul 24, 2023 | 4 T-K Classrooms-Orangewood ES-02-24-000Buildings & facilities | — | — |
| Jul 24, 2023 | 4 T-K Classrooms-Orangewood ES-16-00-000Electrical, low voltage & AV | — | — |
| Jul 24, 2023 | 4 T-K Classrooms-Orangewood ES-02-14-000Buildings & facilities | — | — |
| Jul 24, 2023 | 4 T-K Classrooms-Orangewood ES-02-11-000Demolition & site work | — | — |
| Jul 24, 2023 | Orangewood Elemantary Parking LotOther | — | — |
| Jun 12, 2023 | Kitchen RemodelBuildings & facilities | — | — |
| Apr 3, 2023 | 4 T-K Classrooms-Orangewood ES-13-00-000Buildings & facilities | — | — |
| Apr 3, 2023 | 4 T-K Classrooms-Orangewood ES-CMBuildings & facilities | — | — |
| Jan 31, 2023 | District Admin AdditionBuildings & facilities | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.