Riverside Public Utilities - Electric
299 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Riverside, Riverside County. Reported contract value: $81,899,640.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 25 | $10,165,010 |
| 2025 | 52 | $6,026,104 |
| 2024 | 42 | $65,708,527 |
| 2023 | 29 | — |
| 2022 | 25 | — |
| 2021 | 19 | — |
| 2020 | 21 | — |
| 2019 | 45 | — |
| 2018 | 29 | — |
| 2017 | 5 | — |
| 2016 | 2 | — |
| 2015 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 240
- Traffic & signals · 16
- Electrical, low voltage & AV · 11
- Parks, landscape & fields · 9
- Buildings & facilities · 5
- Sewer & wastewater · 4
- Bridges & structures · 3
- Paving & streets · 3
- Demolition & site work · 2
- Design, inspection & consulting · 2
- Water · 2
- HVAC & mechanical · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| HERMAN WEISSKER INC | 28 | $4,157,716 |
| DOTY BROS. EQUIPMENT CO. DBA DOTY BROS. CONSTRUCTION CO. | 17 | $239,164 |
| W A RASIC CONSTRUCTION COMPANY INC | 10 | $161,852 |
| HOT LINE CONSTRUCTION INC | 8 | $137,003 |
| ASPLUNDH CONSTRUCTION LLC | 6 | $1,054,387 |
| E E ELECTRIC INC | 5 | $67,920 |
| VCI CONSTRUCTION LLC | 5 | $55,581 |
| OUTSOURCE | 2 | $1,155,979 |
| ACT 1 CONSTRUCTION INC | 1 | $9,635,566 |
| OSMOSE UTILITIES SERVICES, INC. | 1 | $1,529,778 |
| EDISON POWER CONSTRUCTORS INC | 1 | $816,321 |
| CORNERSTONECC | 1 | $228,000 |
| FERREIRA CONSTRUCTION CO INC | 1 | $14,200 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Nov 17, 2026 | La Colina Potholing Improvement ProjectOther | HERMAN WEISSKER INC | $10,205 |
| Oct 28, 2026 | Primary Burn Up at 9045 Mandarin Lane.Other | E E ELECTRIC INC | $4,620 |
| Oct 15, 2026 | BTE-4581 Replacement at 11314 Bentley StOther | W A RASIC CONSTRUCTION COMPANY INC | $12,400 |
| Oct 14, 2026 | Secondary Burn Up at 2737 Monroe St.Other | E E ELECTRIC INC | $10,140 |
| Oct 9, 2026 | BTE-4011 Replacement at 9081 Mandarin LnOther | HOT LINE CONSTRUCTION INC | $12,250 |
| Oct 5, 2026 | Conduit Repair for X-5726Parks, landscape & fields | HOT LINE CONSTRUCTION INC | $17,560 |
| Sep 21, 2026 | Primary Burn Up at 6089 Vanessa St.Other | HERMAN WEISSKER INC | $7,670 |
| Sep 17, 2026 | BTE-3146 Repl at 5203 El Cerrito Dr.Other | HOT LINE CONSTRUCTION INC | $12,350 |
| Sep 16, 2026 | Primary Burn Up at 9150 Saguaro Rd.Other | W A RASIC CONSTRUCTION COMPANY INC | $7,852 |
| Sep 16, 2026 | Primary Burn Up at 3778 Park Sierra Dr.Parks, landscape & fields | DOTY BROS. EQUIPMENT CO. DBA DOTY BROS. CONSTRUCTION CO. | $12,204 |
| Sep 9, 2026 | Primary Burn Up at 1225 Spruce St.Other | HOT LINE CONSTRUCTION INC | $7,200 |
| Sep 9, 2026 | Secondary Burn Up at 2820 Gibson St.Other | HERMAN WEISSKER INC | $14,172 |
| Sep 4, 2026 | Primary Burn Up at 8470 Mimosa Tree Ct.Parks, landscape & fields | HERMAN WEISSKER INC | $2,737 |
| Sep 4, 2026 | Secondary Burn Up at 11053 Kayjay St.Other | W A RASIC CONSTRUCTION COMPANY INC | $22,400 |
| Sep 4, 2026 | Primary Burn Up at 4848 Corwin Lane.Other | HERMAN WEISSKER INC | $18,689 |
| Aug 19, 2026 | Primary Burn Up at 8008 Camelot Rd.Other | E E ELECTRIC INC | $9,000 |
| Aug 6, 2026 | Primary Burn Up at 11234 Anaheim St.Other | DOTY BROS. EQUIPMENT CO. DBA DOTY BROS. CONSTRUCTION CO. | $11,000 |
| Jun 30, 2026 | Woodcrest Christian High SchoolElectrical, low voltage & AV | HERMAN WEISSKER INC | $184,292 |
| Jun 29, 2026 | Primary Burn Up at 2560 Prince AlbertOther | W A RASIC CONSTRUCTION COMPANY INC | $20,000 |
| Mar 23, 2026 | La Sierra University TransformerOther | HOT LINE CONSTRUCTION INC | $49,268 |
| Mar 17, 2026 | Secondary Burn Up at 5885 Via CoibaOther | E E ELECTRIC INC | $36,960 |
| Feb 24, 2026 | BTE-2029 & ESB-6 ReplacementOther | HOT LINE CONSTRUCTION INC | $17,275 |
| Feb 11, 2026 | Primary Burn Up at 4423 Carlson Pl.Other | FERREIRA CONSTRUCTION CO INC | $14,200 |
| Jan 16, 2026 | RTRP Site Prep & Street ImprovementsPaving & streets | ACT 1 CONSTRUCTION INC | $9,635,566 |
| Jan 15, 2026 | Primary Burn Up at 3094 Amsterdam Dr.Other | W A RASIC CONSTRUCTION COMPANY INC | $15,000 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.
Do you bid public works?
Find your license and claim your free Atriam profile. It lists the public works projects registered under your license.
Find my license