County of Placer - Department of Public Works
264 public works projects registered with the California Department of Industrial Relations, 2011–2026 · Auburn, Placer County. Reported contract value: $169,039,725.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 7 | $69,767,369 |
| 2025 | 13 | $76,020,932 |
| 2024 | 24 | $22,512,005 |
| 2023 | 32 | $449,419 |
| 2022 | 20 | — |
| 2021 | 36 | — |
| 2020 | 19 | — |
| 2019 | 29 | — |
| 2018 | 22 | — |
| 2017 | 27 | — |
| 2016 | 17 | — |
| 2015 | 10 | — |
| 2014 | 3 | $290,000 |
| 2011 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Paving & streets · 90
- Other · 46
- Bridges & structures · 35
- Parks, landscape & fields · 28
- Traffic & signals · 21
- Sewer & wastewater · 15
- Storm drain & flood control · 10
- Design, inspection & consulting · 10
- Buildings & facilities · 4
- Concrete & masonry · 2
- Electrical, low voltage & AV · 1
- Demolition & site work · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| ALL-AMERICAN CONSTRUCTION INC | 2 | $3,383,324 |
| PAVEMENT COATINGS CO | 2 | $2,379,500 |
| GOLDEN STATE STRIPING & SIGNS | 2 | $490,000 |
| FLATIRON DRAGADOS WEST LLC | 1 | $55,506,762 |
| KCM Engineering, Inc. | 1 | $8,883,385 |
| AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC | 1 | $1,959,000 |
| AMERICAN PAVING CO | 1 | $1,398,872 |
| F B D VANGUARD CONSTRUCTION INC | 1 | $1,371,695 |
| CONSOLIDATED ENGINEERING INC | 1 | $685,562 |
| Q&D CONSTRUCTION LLC | 1 | $598,000 |
| MYERS & SONS CONSTRUCTION LLC | 1 | $485,418 |
| CALTECH ENVIRONMENTAL CONSTRUCTION INC | 1 | $134,461 |
| BALDONI CONSTRUCTION SERVICE INC A CALIFORNIA CORPORATION | 1 | $116,000 |
| NV5, INC. | 1 | $21,471 |
| NORTHERN STATE LAND MANAGEMENT | 1 | $12,650 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 30, 2026 | 2026 Roadway Surface Treatment ProjectPaving & streets | AMERICAN PAVING CO | $1,398,872 |
| Jun 30, 2026 | Wexford Lift Station Improvement ProjectSewer & wastewater | KOCH & KOCH INC | $2,105,275 |
| Jun 30, 2026 | HSIP Cycle 12 - High Friction Surface TrPaving & streets | AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC | $1,959,000 |
| Jun 30, 2026 | 2026 Hot Mix Asphalt Overlay ProjectPaving & streets | CONSOLIDATED ENGINEERING INC | $685,562 |
| Jun 2, 2026 | ERMRF Pavement Repairs Project, Phase 2Storm drain & flood control | Q&D CONSTRUCTION LLC | $598,000 |
| Jun 1, 2026 | Meadow Vista Walkway ProjectTraffic & signals | F B D VANGUARD CONSTRUCTION INC | $1,371,695 |
| Apr 7, 2026 | Placer Parkway Phase 1Bridges & structures | TEICHERT CONSTRUCTION | $61,648,965 |
| Aug 27, 2025 | Demo of Existing Structures 1281 Dog BarSewer & wastewater | CALTECH ENVIRONMENTAL CONSTRUCTION INC | $134,461 |
| Aug 5, 2025 | American River Debris Removal (Con)Other | — | $5,044,040 |
| Jun 12, 2025 | Tahoe Pedestrian FlaggersOther | — | $223,156 |
| Jun 10, 2025 | 2025 Surface TreatmentsPaving & streets | PAVEMENT COATINGS CO | $1,629,355 |
| Jun 10, 2025 | 2025 ROADWAY HOT MIX ASPHALT OVERLAYPaving & streets | — | $1,933,777 |
| Jun 10, 2025 | ERL Pavement Repair Project Phase 1 MRFSewer & wastewater | ALL-AMERICAN CONSTRUCTION INC | $851,147 |
| May 27, 2025 | Horseshoe Bar Lift Station Impr ProjectSewer & wastewater | — | $647,907 |
| May 13, 2025 | Dry Creek at Rock Creek Bridge RehabBridges & structures | Wood Rodgers Inc | $975,941 |
| Apr 16, 2025 | Lower Sawtooth Trailhead ImprovementOther | BALDONI CONSTRUCTION SERVICE INC A CALIFORNIA CORPORATION | $116,000 |
| Mar 11, 2025 | Yankee Jims Bridge Replacement ProjectBridges & structures | FLATIRON DRAGADOS WEST LLC | $55,506,762 |
| Mar 1, 2025 | Kings Beach Core Parking Lot MaintenanceOther | — | $25,000 |
| Mar 1, 2025 | Kings Beach Landscape MaintenanceParks, landscape & fields | — | $50,000 |
| Jan 21, 2025 | Yankee Jims Bridge Replacement ProjectBridges & structures | KCM Engineering, Inc. | $8,883,385 |
| Oct 22, 2024 | Highway 49 Wastewater Capacity Proj- Ph1Sewer & wastewater | UNICO Engineering, Inc. | $1,198,698 |
| Oct 22, 2024 | Highway 49 Wastewater Capacity Proj- Ph1Sewer & wastewater | — | $10,786,241 |
| Sep 24, 2024 | HSIP Cycle 11 Guardrail & CenterlineTraffic & signals | — | $367,270 |
| Sep 16, 2024 | Sheridan Pond Liner RepairConcrete & masonry | — | $17,000 |
| Sep 10, 2024 | Kings Beach Bench RestorationOther | NORTHERN STATE LAND MANAGEMENT | $12,650 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.