Lake County Special Districts
39 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Lakeport, Lake County. Reported contract value: $1,039,171.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 6 | $518,995 |
| 2025 | 6 | $225,372 |
| 2024 | 5 | — |
| 2023 | 2 | — |
| 2022 | 3 | — |
| 2021 | 1 | — |
| 2020 | 1 | — |
| 2017 | 3 | — |
| 2016 | 5 | — |
| 2015 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Water · 13
- Sewer & wastewater · 11
- Other · 7
- Electrical, low voltage & AV · 3
- Traffic & signals · 2
- Bridges & structures · 2
- Roofing · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| Woida Ent inc dba Arrow Fencing | 4 | $27,497 |
| CORNWELL ELECTRIC LLC | 3 | $125,529 |
| WEEKS DRILLING AND PUMP COMPANY | 2 | $105,884 |
| TERRACON CONSTRUCTORS INC | 1 | $338,968 |
| CARBON ACTIVATED CORPORATION | 1 | $169,275 |
| LiquiVision Technology Inc | 1 | $62,000 |
| MATHEWS MECHANICAL | 1 | $43,700 |
| DALLAS WOLL INC DBA ROTO ROOTER OF LAKE COUNTY | 1 | $9,614 |
| PERFORMANCE MECHANICAL INC | 1 | $6,704 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jul 28, 2026 | NW LS17 Generator FencingSewer & wastewater | Woida Ent inc dba Arrow Fencing | $6,758 |
| Jul 28, 2026 | NW LS16 Generator FencingSewer & wastewater | Woida Ent inc dba Arrow Fencing | $9,456 |
| Jul 28, 2026 | NW LS15 Generator FencingElectrical, low voltage & AV | Woida Ent inc dba Arrow Fencing | $4,200 |
| May 18, 2026 | Live Oak Water Line ReplacementTraffic & signals | TERRACON CONSTRUCTORS INC | $338,968 |
| Mar 31, 2026 | Lift Station #1 Surge Tank PlumbingSewer & wastewater | DALLAS WOLL INC DBA ROTO ROOTER OF LAKE COUNTY | $9,614 |
| Jan 11, 2026 | Emergency Work- Robin Lane Sewer SpillSewer & wastewater | — | $150,000 |
| Nov 21, 2025 | Spring Valley Well Pump and Tie-InWater | WEEKS DRILLING AND PUMP COMPANY | $69,934 |
| Nov 21, 2025 | North Lakeport Well Pump & Tie-InWater | WEEKS DRILLING AND PUMP COMPANY | $35,950 |
| Oct 7, 2025 | LS#2 Wet Well Pit RepairWater | MATHEWS MECHANICAL | $43,700 |
| Oct 7, 2025 | LS#5 NW Fence RepairSewer & wastewater | Woida Ent inc dba Arrow Fencing | $7,083 |
| Oct 1, 2025 | LS#12 Lid Replacement ProjectOther | PERFORMANCE MECHANICAL INC | $6,704 |
| Sep 24, 2025 | Tank CleaningWater | LiquiVision Technology Inc | $62,000 |
| Apr 8, 2024 | Adobe Creek Bridge Crossing - 2024Bridges & structures | — | — |
| Apr 1, 2024 | SE EMT Building Roof Repairs - 2024Roofing | — | — |
| Apr 1, 2024 | Kono Tank 1 GateOther | — | — |
| Mar 18, 2024 | Fence at Lift Station 7 SoutheastSewer & wastewater | — | — |
| Jan 8, 2024 | Fence Repairs - UA2 Lift Stations - 2024Sewer & wastewater | — | — |
| Dec 13, 2023 | SE Transformer and SWGR testingOther | — | — |
| Mar 27, 2023 | SDA Fiber Optic CableOther | — | — |
| Aug 29, 2022 | CSA 2 Spring Valley Water Quail TrailWater | — | — |
| Aug 10, 2022 | Quail Trail Construction StakingWater | — | — |
| Jul 1, 2022 | Live Oak Water Main ReplacementWater | — | — |
| Aug 16, 2021 | Adobe Creek Bridge Temporary Water MainBridges & structures | — | — |
| Aug 10, 2020 | Soda Bay CSA-20 Redwood Water Tank ReplaWater | — | — |
| Dec 31, 2017 | Clearlake Oaks Intertie Control Valve PrOther | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.