82 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Linden, San Joaquin County. Reported contract value: $659,527.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 1 | $37,537 |
| 2025 | 5 | $435,950 |
| 2024 | 2 | $94,120 |
| 2023 | 5 | — |
| 2022 | 11 | — |
| 2021 | 3 | — |
| 2020 | 2 | — |
| 2019 | 6 | — |
| 2017 | 21 | — |
| 2016 | 20 | — |
| 2015 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 16
- Parks, landscape & fields · 11
- Electrical, low voltage & AV · 10
- Paving & streets · 10
- HVAC & mechanical · 6
- Plumbing & restrooms · 6
- Painting & flooring · 5
- Other · 5
- Roofing · 4
- Concrete & masonry · 2
- Water · 2
- Sewer & wastewater · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| JAHN BUILDERS | 2 | $134,404 |
| JOHNSON CONTROLS FIRE PROTECTION LP | 1 | $94,120 |
| DRYCO CONSTRUCTION INC | 1 | $37,537 |
| MID PACIFIC ENGINEERING, INC. | 1 | $7,500 |
| CONDOR EARTH TECHNOLOGIES, INC. | 1 | $4,231 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jul 2, 2026 | Glenwood- Seal Coat & Stripe: 2026Traffic & signals | DRYCO CONSTRUCTION INC | $37,537 |
| Oct 19, 2025 | Relocatable Building at Waverly ElBuildings & facilities | — | $134,080 |
| Sep 24, 2025 | Waverly Classroom Addition Material TestDesign, inspection & consulting | CONDOR EARTH TECHNOLOGIES, INC. | $4,231 |
| May 27, 2025 | Sewer Lift stationSewer & wastewater | JAHN BUILDERS | $49,984 |
| Mar 27, 2025 | Waterloo Seal Coat & Stripe 2025Paving & streets | — | $44,425 |
| Mar 21, 2025 | CalSHAPE MEchanical ServicesHVAC & mechanical | — | $203,230 |
| Oct 11, 2024 | LHS Fire Panel ReplacementBuildings & facilities | JOHNSON CONTROLS FIRE PROTECTION LP | $94,120 |
| Jun 3, 2024 | LHS IT DEPT. E-Rate 26 - Network UpgradeElectrical, low voltage & AV | — | — |
| Jul 6, 2023 | LHS Preschool RestroomPlumbing & restrooms | — | — |
| Jun 12, 2023 | Transportation AsphaltPaving & streets | — | — |
| Apr 1, 2023 | Portable MakeoverBuildings & facilities | — | — |
| Apr 1, 2023 | Clocks/Bells/PA ElementaryBuildings & facilities | — | — |
| Jan 2, 2023 | Water & Fire Supp. ConnectionOther | — | — |
| Nov 17, 2022 | Accessible Path/Fencing School FarmBuildings & facilities | — | — |
| Jul 5, 2022 | Lighting room #15 LHSElectrical, low voltage & AV | — | — |
| Jun 10, 2022 | East-Wing Walkway CoverOther | — | — |
| Jun 10, 2022 | 4to6 FencingBuildings & facilities | — | — |
| May 2, 2022 | Play Ground Replace GlenwoodParks, landscape & fields | — | — |
| Apr 23, 2022 | Linden SolarSolar, EV & energy | — | — |
| Apr 11, 2022 | Stadium Light TowersBuildings & facilities | — | — |
| Mar 22, 2022 | Walls Glenwood ElementaryBuildings & facilities | — | — |
| Mar 21, 2022 | Classroom walls Glenwood SchoolBuildings & facilities | — | — |
| Mar 15, 2022 | Classroom walls Linden ElementaryBuildings & facilities | — | — |
| Feb 21, 2022 | Portable walls Waverly ElementaryBuildings & facilities | — | — |
| Dec 31, 2021 | Bus Charging StationsElectrical, low voltage & AV | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.