Projects by year

YearProjectsReported contract value
20267$2,267,504
20253$1,301,054
202412$4,493,246
20236—
20229—
20218—
20202—
20194—
20184—
20171—
20166—
20153—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Water · 40
  • Sewer & wastewater · 13
  • Other · 5
  • Paving & streets · 3
  • Demolition & site work · 2
  • Buildings & facilities · 1
  • Painting & flooring · 1
  • Concrete & masonry · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
T E ROBERTS INC7$2,271,539
BIG BEN INC2$1,507,661
COAST SURVEYING, INC.1$1,265,000
J. A. SALAZAR CONSTRUCTION AND SUPPLY CO1$516,886
URETEK USA, INC.1$199,925
BEST DRILLING AND PUMP INC1$97,855
GUIDA SURVEYING INC.1$30,000

Latest projects

DateProjectPrime contractorContract amount
May 14, 2026Golden Avenue Waterline ImprovementsWaterT E ROBERTS INC$294,157
May 14, 2026Kellogg Dr Water and Sewer RplcmntSewer & wastewaterCOAST SURVEYING, INC.$1,265,000
Apr 20, 2026Imperial HWY and Casa Loma Road RepairsPaving & streetsT E ROBERTS INC$27,350
Apr 13, 2026Road Settlement Repairs at Imperial HwyPaving & streetsT E ROBERTS INC$27,350
Jan 8, 2026LAKEVIEW RESERVOIR LOCALIZED SLOPE STABIWaterURETEK USA, INC.$199,925
Jan 8, 2026Blue Ridge Drive/Castle Bend Way WaterliWaterT E ROBERTS INC$250,000
Jan 8, 2026Blue Ridge-Castle Bend_Waterline RehabilWaterT E ROBERTS INC$203,722
Oct 13, 2025Santiago BPS Discharge Pipe LiningDemolition & site workT E ROBERTS INC$686,313
Sep 11, 2025Well 18 RehabilitationWaterBEST DRILLING AND PUMP INC$97,855
Apr 10, 2025FY24-25 Fire Flow Enhancement at PYLUSDWaterJ. A. SALAZAR CONSTRUCTION AND SUPPLY CO$516,886
Dec 12, 2024FF-4, FF-7 & FF-12 FIRE FLOW ENHANCEMENTWaterBIG BEN INC$1,408,741
Dec 12, 2024FF-1 Waterline Replacements in PlacentiaWater——
Dec 12, 2024Golden Avenue ACP RemovalDemolition & site workBIG BEN INC$98,920
Dec 12, 2024Well 21 RehabilitationWater—$65,639
Nov 14, 2024FF-11 Waterline & Adobe PRS ReplacementWater—$1,131,983
Nov 14, 2024Box Canyon 16" Waterline ImprovementsWaterT E ROBERTS INC$782,646
Aug 8, 2024Camino De Bryant Waterline Rplcmnt Ph. 2Water—$1,005,318
Mar 25, 2024Elk Mountain BPS Leak RepairOther——
Feb 19, 2024FY23-24 Pressure Regulating Station ReplOther——
Feb 14, 2024Well 5 RehabilitationWater——
Jan 22, 2024Camino De Bryant Waterline Replacement PWater——
Jan 18, 2024Main Street Sewer ReplacementSewer & wastewater——
Dec 28, 2023Well 19 Rehabilitation Phase 1Water——
Dec 18, 2023FY23-24 Sewer CIPP RehabilitationSewer & wastewater——
Jul 1, 2023Imperial Waterline ImprovementsWater——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.