County of Orange/OC Public Works
4685 public works projects registered with the California Department of Industrial Relations, 2014–2026 · Santa Ana, Orange County. Reported contract value: $787,429,552.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2029 | 1 | $1,000,000 |
| 2027 | 1 | $56,900 |
| 2026 | 167 | $213,159,258 |
| 2025 | 189 | $71,774,846 |
| 2024 | 275 | $118,888,284 |
| 2023 | 299 | $345,037,668 |
| 2022 | 383 | $9,839,020 |
| 2021 | 460 | — |
| 2020 | 582 | — |
| 2019 | 519 | $1,108,420 |
| 2018 | 490 | — |
| 2017 | 523 | — |
| 2016 | 442 | — |
| 2015 | 280 | — |
| 2014 | 3 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 1496
- Buildings & facilities · 673
- Paving & streets · 448
- Parks, landscape & fields · 385
- Painting & flooring · 285
- Electrical, low voltage & AV · 249
- HVAC & mechanical · 172
- Bridges & structures · 161
- Plumbing & restrooms · 145
- Roofing · 133
- Design, inspection & consulting · 88
- Storm drain & flood control · 85
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| BITECH CONSTRUCTION CO., INC. | 22 | $15,640,976 |
| Carmody Construction Company | 20 | $785,937 |
| H L MILLER INC | 16 | $739,355 |
| NINYO & MOORE GEOTECHNICAL & ENVIRONMENTAL SCIENCES CONSULTANTS | 14 | $586,857 |
| PRIME ENC INC | 12 | $2,556,140 |
| KLEINFELDER INC | 12 | $669,855 |
| Omega Construction Services, Inc. | 11 | $7,449,491 |
| ABM BUILDING SOLUTIONS, LLC | 11 | $4,759,848 |
| OMEGA CONSTRUCTION CO INC | 10 | $3,715,172 |
| HORIZONS CONSTRUCTION COMPANY INTERNATIONAL INC | 10 | $2,087,649 |
| EXCEL PAVING COMPANY | 9 | $13,328,179 |
| MATCON GENERAL ENGINEERING INC | 9 | $9,778,935 |
| MTM CONSTRUCTION INC | 9 | $5,404,255 |
| HARRY H JOH CONSTRUCTION INC | 9 | $3,529,569 |
| GMU GEOTECHNICAL, INC. | 9 | $269,503 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Nov 18, 2029 | Gas Compressor Maintenance and RepairOther | AMTEK CONSTRUCTION— | $1,000,000 |
| Apr 30, 2027 | Ralph B Clark Regional Park MaintenanceHVAC & mechanical | APPLIED AIR CONDITIONING INC. | $56,900 |
| Nov 17, 2026 | JUVENILE HALL REDEVELOPMENT PHASE II PROBuildings & facilities | BALFOUR BEATTY CONSTRUCTION LLC | $132,826,735 |
| Nov 16, 2026 | Laguna Niguel Regional Park Mainline IrrParks, landscape & fields | VERNE'S PLUMBING INC | $28,963 |
| Nov 10, 2026 | Juvenile Hall-MRC KitchenBuildings & facilities | MTM CONSTRUCTION INC | $433,189 |
| Nov 10, 2026 | JOC: San Juan Creek Channel (L01) RepairOther | K E C ENGINEERING | $970,876 |
| Nov 10, 2026 | Juvenile Hall Replace Kitchen AC, Make UBuildings & facilities | MTM CONSTRUCTION INC | $798,677 |
| Nov 5, 2026 | OOCH – Glass Block Porch ReplacementDesign, inspection & consulting | Thirtieth Street Architects, Inc. | $42,300 |
| Nov 5, 2026 | Old County Courthouse - Glass Block PorcDesign, inspection & consulting | Thirtieth Street Architects, Inc. | $42,300 |
| Nov 3, 2026 | CEO – Data Center (30611) – Replace (3)Water | VERNE'S PLUMBING INC | $73,940 |
| Nov 3, 2026 | 1055 Main Air Handler #1 Repair, Aim #12Other | ACCO ENGINEERED SYSTEMS | $153,292 |
| Nov 2, 2026 | CTO: ADA UPGRADES LADERA RANCHDesign, inspection & consulting | Onward Engineering | $4,440 |
| Oct 28, 2026 | Cove Room Lighting ReplacementElectrical, low voltage & AV | WILLIAMS & MAHER INC | $33,148 |
| Oct 27, 2026 | 7-Year Roadway Analysis and Distress SurPaving & streets | NICHOLS CONSULTING ENGINEERS, CHTD | $564,433 |
| Oct 26, 2026 | JOC: OCSD GATES BUILDING ROOM 561 - PRE-Buildings & facilities | PRIME ENC INC | $251,962 |
| Oct 26, 2026 | Dana Point Library Sewer ReplacementSewer & wastewater | VERNE'S PLUMBING INC | $43,260 |
| Oct 26, 2026 | JOC: Traffic Signal Upgrades - EsperanzaTraffic & signals | BITECH CONSTRUCTION CO., INC. | $290,658 |
| Oct 20, 2026 | OCCR - Capistrano maintenance shed roofRoofing | BISHOP INC | $20,041 |
| Oct 20, 2026 | CTO: COC C-ROV WarhouseHVAC & mechanical | IDS GROUP, INC. | $106,984 |
| Oct 14, 2026 | JOC: Esperanza Channel (E06) Emergency ROther | EXCEL PAVING COMPANY | $70,835 |
| Oct 12, 2026 | OCCR – Los Alamitos Library DrainsBuildings & facilities | VINCOR CONSTRUCTION INC | $36,184 |
| Oct 8, 2026 | Las Flores Road Improvement (EQ20006C)Paving & streets | Onward Engineering | $47,360 |
| Oct 7, 2026 | Santiago Canyon Road Bridge Over WilliamBridges & structures | EXBON DEVELOPMENT INC | $408,633 |
| Sep 29, 2026 | SANTA ANA RIVER (E01) AVIO TIDE GATES REOther | POWER ENGINEERING CONSTRUCTION COMPANY | $95,300 |
| Sep 28, 2026 | ONE TIME FOR - REPLACE DAMAGE IRRIGATIONParks, landscape & fields | PRO - CRAFT CONSTRUCTION INC | $67,561 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.
Do you bid public works?
Find your license and claim your free Atriam profile. It lists the public works projects registered under your license.
Find my license