152 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Redding, Shasta County. Reported contract value: $10,582,732.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 29 | $3,090,993 |
| 2025 | 31 | $6,861,369 |
| 2024 | 7 | $452,904 |
| 2023 | 1 | $177,466 |
| 2018 | 1 | — |
| 2017 | 51 | — |
| 2016 | 28 | — |
| 2015 | 3 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Buildings & facilities · 29
- Other · 23
- HVAC & mechanical · 17
- Painting & flooring · 15
- Parks, landscape & fields · 14
- Paving & streets · 10
- Roofing · 8
- Electrical, low voltage & AV · 7
- Plumbing & restrooms · 6
- Demolition & site work · 5
- Storm drain & flood control · 4
- Concrete & masonry · 3
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| ARBISO'S ASPHALT SERVICES | 5 | $115,462 |
| FLEXGROUND LLC | 4 | $139,083 |
| PLAYCORE WISCONSIN, INC. | 3 | $716,867 |
| THE TRENCHLESS COMPANY | 3 | $139,687 |
| JOHN JAXON CONSTRUCTION | 3 | $103,292 |
| WALGAMUTH PAINTING INC | 3 | $55,670 |
| EDDIE AXNER CONSTRUCTION, INC. | 2 | $412,002 |
| NORTHSTATE EARTH AND WATER INC | 2 | $115,725 |
| DOUG SHERMAN ELECTRIC | 2 | $83,201 |
| PHILIP LESLIE CARPENTER | 2 | $78,100 |
| IRON MOUNTAIN GENERAL ENGINEERING INC | 2 | $72,986 |
| HANES FLOOR INCORPORATED | 2 | $46,808 |
| CERAMI & BROWNING CONSTRUCTION INC | 1 | $1,485,000 |
| LAMB UNLIMITED GENERAL ENGINEERING | 1 | $254,540 |
| CRBR PROPERTY DAMAGE SERVICES | 1 | $75,000 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Dec 21, 2026 | Parsons trenchless pipe phase 2Buildings & facilities | THE TRENCHLESS COMPANY | $63,173 |
| Dec 21, 2026 | Lassen View Lossnay ERV rooms 6, 7, 8HVAC & mechanical | PHIL CARPENTER'S A/C & HEATING | $46,595 |
| Oct 1, 2026 | Lassen View Kinder playgroundParks, landscape & fields | FLEXGROUND LLC | $29,880 |
| Oct 1, 2026 | Alta Mesa main playground renovationParks, landscape & fields | NORTHSTATE EARTH AND WATER INC | $66,926 |
| Jul 7, 2026 | Parsons Jr. High school trenchless pipeBuildings & facilities | THE TRENCHLESS COMPANY | $40,904 |
| Jul 7, 2026 | Rother School trenchless pipe liningBuildings & facilities | THE TRENCHLESS COMPANY | $35,610 |
| Jul 6, 2026 | EESD District office roof replacementDesign, inspection & consulting | HARBERT ROOFING, INC. | $41,670 |
| Jul 1, 2026 | Monte Vista asphalt sealcoat maintenancePaving & streets | ARBISO'S ASPHALT SERVICES | $22,922 |
| Jun 15, 2026 | Lassen View School utility projectBuildings & facilities | EDDIE AXNER CONSTRUCTION, INC. | $365,856 |
| Jun 10, 2026 | Parsons Jr. High carpet replacementPainting & flooring | HANES FLOOR INCORPORATED | $27,913 |
| Jun 10, 2026 | Shasta Meadows ventilation rms 1,3,4 & 5HVAC & mechanical | PHILIP LESLIE CARPENTER | $52,000 |
| Jun 10, 2026 | BC main playground swing setParks, landscape & fields | JOHN JAXON CONSTRUCTION | $25,527 |
| Jun 10, 2026 | Shasta Meadows playground haul offParks, landscape & fields | JOHN JAXON CONSTRUCTION | $45,565 |
| Jun 10, 2026 | Restroom floor prep and expoxyPlumbing & restrooms | WALGAMUTH PAINTING INC | $22,120 |
| Jun 10, 2026 | Restroom floor prep and expoxyPlumbing & restrooms | WALGAMUTH PAINTING INC | $15,750 |
| Jun 10, 2026 | PACE School/MV carpet replacementPainting & flooring | HANES FLOOR INCORPORATED | $18,895 |
| Jun 10, 2026 | Alta Mesa asphalt sealcoat & restripePaving & streets | ARBISO'S ASPHALT SERVICES | $26,835 |
| Jun 10, 2026 | BC PRESCHOOL PLAYGROUNDParks, landscape & fields | JOHN JAXON CONSTRUCTION | $32,200 |
| Jun 10, 2026 | Rother restroom floor epoxyPlumbing & restrooms | WALGAMUTH PAINTING INC | $17,800 |
| Jun 10, 2026 | Mistletoe Irrigation LineElectrical, low voltage & AV | IRON MOUNTAIN GENERAL ENGINEERING INC | $33,880 |
| Jun 8, 2026 | Shasta Meadows sewer repair in backSewer & wastewater | IRON MOUNTAIN GENERAL ENGINEERING INC | $39,106 |
| Jun 8, 2026 | Lassen View 600a 3 phase circuitBuildings & facilities | DOUG SHERMAN ELECTRIC | $55,371 |
| Jun 8, 2026 | Lassen View conduit relocationOther | DOUG SHERMAN ELECTRIC | $27,831 |
| May 11, 2026 | Boulder Creek Music Classroom 2026Buildings & facilities | CERAMI & BROWNING CONSTRUCTION INC | $1,485,000 |
| Apr 6, 2026 | SM Room 6&7 ventilationHVAC & mechanical | PHILIP LESLIE CARPENTER | $26,100 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.
Do you bid public works?
Find your license and claim your free Atriam profile. It lists the public works projects registered under your license.
Find my license