City of San Luis Obispo
6 public works projects registered with the California Department of Industrial Relations, 2025–2026 · San Luis Obispo, San Luis Obispo County. Reported contract value: $998,237.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 5 | $708,237 |
| 2025 | 1 | $290,000 |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Water · 2
- Other · 1
- Sewer & wastewater · 1
- Fire & life safety · 1
- Concrete & masonry · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| GREGG DRILLING LLC | 1 | $443,562 |
| MIDCAL DREDGING INC | 1 | $290,000 |
| W M LYLES CO | 1 | $212,670 |
| JF BRENNAN COMPANY INC | 1 | $35,099 |
| JOHNSON CONTROLS FIRE PROTECTION LP | 1 | $10,711 |
| FARWEST CORROSION CONTROL COMPANY | 1 | $6,195 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 1, 2026 | WRRF - Structure 44 Fire Alarm ControlsFire & life safety | JOHNSON CONTROLS FIRE PROTECTION LP | $10,711 |
| Mar 31, 2026 | WTP Ozone Containment ImprovementSewer & wastewater | W M LYLES CO | $212,670 |
| Feb 19, 2026 | TCE Plume Characterization - Packet 1Water | GREGG DRILLING LLC | $443,562 |
| Feb 2, 2026 | Whale Rock Reservoir Intake Valve RepairWater | JF BRENNAN COMPANY INC | $35,099 |
| Jan 28, 2026 | Tank Corrosion Protection and Maint.Other | FARWEST CORROSION CONTROL COMPANY | $6,195 |
| Jul 8, 2025 | Whale Rock Stilling Basin DewateringConcrete & masonry | MIDCAL DREDGING INC | $290,000 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.