70 public works projects registered with the California Department of Industrial Relations, 2017–2026 · Santa Barbara, Santa Barbara County. Reported contract value: $4,969,422.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 7 | $1,355,143 |
| 2025 | 12 | $537,162 |
| 2024 | 13 | $3,077,117 |
| 2023 | 14 | — |
| 2022 | 8 | — |
| 2021 | 10 | — |
| 2019 | 3 | — |
| 2017 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 15
- Parks, landscape & fields · 10
- Buildings & facilities · 8
- Electrical, low voltage & AV · 8
- Roofing · 4
- Sewer & wastewater · 4
- Storm drain & flood control · 4
- Demolition & site work · 3
- HVAC & mechanical · 3
- Paving & streets · 3
- Painting & flooring · 2
- Plumbing & restrooms · 2
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| FRANK SCHIPPER CONSTRUCTION CO | 8 | $496,417 |
| CHALLENGE ASPHALT INC | 2 | $144,569 |
| WRIGHT SAWING & BREAKING INC DBA WRIGHT SAWING & BREAKING | 2 | $57,642 |
| SCOTT AND SONS ELECTRIC | 1 | $700,000 |
| JIMENEZ PAINTING COMPANY | 1 | $311,800 |
| M/M MECHANICAL INC | 1 | $58,704 |
| JAV INC | 1 | $53,592 |
| COMMERCIAL FLOORING SOLUTIONS BY ACR | 1 | $47,947 |
| CRAIG ROOF COMPANY INC | 1 | $39,429 |
| KAMRAN AND COMPANY LLC | 1 | $29,499 |
| MESA ENERGY SYSTEMS INC | 1 | $28,421 |
| PACIFIC ONESOURCE INC | 1 | $27,747 |
| COURT VIDEO CONFERENCING SERVICES LIMITED LIABILITY COMPANY | 1 | $23,089 |
| EARTH SYSTEMS PACIFIC | 1 | $21,500 |
| SANTA BARBARA LOCKSMITHS INC | 1 | $19,409 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 8, 2026 | ASPHALT REPAIRS AT HOPE ESPaving & streets | CHALLENGE ASPHALT INC | $73,011 |
| May 11, 2026 | DISTRICT-WIDE SWITCHGEAR REPLACEMENTElectrical, low voltage & AV | SCOTT AND SONS ELECTRIC | $700,000 |
| May 11, 2026 | SEWER IMPROVEMENT REPLACEMENT AT VVSewer & wastewater | FRANK SCHIPPER CONSTRUCTION CO | $147,231 |
| May 11, 2026 | DISTRICT-WIDE EXTERIOR PAINTINGPainting & flooring | JIMENEZ PAINTING COMPANY | $311,800 |
| Mar 9, 2026 | Hope Elementary Modular Foundation, SlabDemolition & site work | FRANK SCHIPPER CONSTRUCTION CO | $55,745 |
| Mar 9, 2026 | REMOVAL AND INSTALL LVT FLOORING AT MVDemolition & site work | COMMERCIAL FLOORING SOLUTIONS BY ACR | $47,947 |
| Feb 9, 2026 | HOPE ES EXTERIOR RE-KEYBuildings & facilities | SANTA BARBARA LOCKSMITHS INC | $19,409 |
| Oct 20, 2025 | HES S40 Soils ReportBuildings & facilities | EARTH SYSTEMS PACIFIC | $21,500 |
| Oct 20, 2025 | PERGOLA REPLACEMENT AT HOPE ESOther | FRANK SCHIPPER CONSTRUCTION CO | $74,474 |
| Oct 20, 2025 | CARETAKER'S CLEARING & UTILITIES AT HESBuildings & facilities | WRIGHT SAWING & BREAKING INC DBA WRIGHT SAWING & BREAKING | $33,062 |
| Aug 11, 2025 | EXHAUST VENTILATION DISTRICT-WIDEHVAC & mechanical | FRANK SCHIPPER CONSTRUCTION CO | $41,649 |
| Aug 11, 2025 | DEMOLITION OF CARETAKER'S HOUSEDemolition & site work | WRIGHT SAWING & BREAKING INC DBA WRIGHT SAWING & BREAKING | $24,580 |
| Jun 9, 2025 | A/V UPGRADES AT HOPE ES MPRElectrical, low voltage & AV | JAV INC | $53,592 |
| Jun 9, 2025 | WATER INTRUSION AND IDF AT N40 HESBuildings & facilities | FRANK SCHIPPER CONSTRUCTION CO | $42,768 |
| May 12, 2025 | REPAIR CONCRETE FLATWORK AT MONTE VISTAConcrete & masonry | FRANK SCHIPPER CONSTRUCTION CO | $42,051 |
| May 12, 2025 | ROOFING REPLACEMENTRoofing | CRAIG ROOF COMPANY INC | $39,429 |
| May 12, 2025 | Kitchen and Storage Room Floor RepairOther | FRANK SCHIPPER CONSTRUCTION CO | $69,576 |
| Apr 14, 2025 | Asphalt Repairs for Monte Vista & VVPaving & streets | CHALLENGE ASPHALT INC | $71,558 |
| Mar 17, 2025 | Repair Storm Drain at Vieja ValleyStorm drain & flood control | FRANK SCHIPPER CONSTRUCTION CO | $22,923 |
| Dec 8, 2024 | Furniture Purchase & InstallationOther | — | $219,690 |
| Nov 18, 2024 | MV BOTTLE FILLERSOther | MESA ENERGY SYSTEMS INC | $28,421 |
| Nov 18, 2024 | DISTRICT-WIDE INSTALL 10 CAMERASOther | PACIFIC ONESOURCE INC | $27,747 |
| Oct 21, 2024 | DISTRICT WIDE PA AUDIO SYSTEM UPGRADEElectrical, low voltage & AV | COURT VIDEO CONFERENCING SERVICES LIMITED LIABILITY COMPANY | $23,089 |
| Oct 21, 2024 | DISTRICT WIDE IT INFRASTRUCTURE UPGRADESOther | — | $59,850 |
| Oct 21, 2024 | DISTRICT-WIDE TREE TRIMMINGRoofing | — | $23,580 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.