Calaveras Public Utility District
13 public works projects registered with the California Department of Industrial Relations, 2015–2026 · San Andreas. Reported contract value: $407,320.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 1 | $407,320 |
| 2023 | 1 | — |
| 2021 | 2 | — |
| 2020 | 2 | — |
| 2019 | 1 | — |
| 2017 | 1 | — |
| 2016 | 3 | — |
| 2015 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Water · 5
- Other · 4
- Parks, landscape & fields · 1
- Paving & streets · 1
- Buildings & facilities · 1
- Storm drain & flood control · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| MOZINGO CONSTRUCTION, INC. | 1 | $407,320 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Aug 27, 2026 | Rich Gulch Waterline Replacement ProjectWater | MOZINGO CONSTRUCTION, INC. | $407,320 |
| Apr 17, 2023 | Filter Media AdditionBuildings & facilities | — | — |
| Aug 23, 2021 | Clearwell Tank Proj. Ph.1 Site ImprovemeParks, landscape & fields | — | — |
| Aug 23, 2021 | Clearwell Tank Proj. Ph.2Other | — | — |
| Sep 8, 2020 | 2019 FEMA Storm Damage RepairStorm drain & flood control | — | — |
| Jun 22, 2020 | Court Street Line Replacement ProjectWater | — | — |
| May 6, 2019 | SCADAOther | — | — |
| Aug 10, 2017 | Sunset Street Waterline ReplacementWater | — | — |
| Sep 23, 2016 | Magnolia Way Marlar Leak repairOther | — | — |
| Sep 6, 2016 | High School Street repairPaving & streets | — | — |
| May 2, 2016 | Filter Media Replacement at Jeff Davis WOther | — | — |
| Apr 28, 2015 | South Main StreetWater | — | — |
| — | South Main Street, Mokelumne HillWater | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.