YearProjectsReported contract value
20262$2,052,416
20254$3,163,134
20244$100,900
20233—
20222—
20211—
20209—
20198—
20188—
20176—
20167—
20156—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 23
  • Buildings & facilities · 9
  • Electrical, low voltage & AV · 8
  • Paving & streets · 6
  • Demolition & site work · 4
  • Roofing · 3
  • Concrete & masonry · 2
  • Solar, EV & energy · 2
  • HVAC & mechanical · 1
  • Painting & flooring · 1
  • Plumbing & restrooms · 1
  • Fire & life safety · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
VANCE CORPORATION1$1,936,169
THREE PEAKS CORP.1$492,864
EVERON LLC1$261,374
Cryogenic Industries LLC1$116,247
COPP ROOFING & CONSTRUCTION INC.1$30,970

Latest projects

DateProjectPrime contractorContract amount
Sep 1, 2026IFB 27-010 (2 CNG Dispensers)Electrical, low voltage & AVCryogenic Industries LLC$116,247
Mar 9, 202625-006 Asphalt Concrete Pavement UpgradePaving & streetsVANCE CORPORATION$1,936,169
Nov 17, 2025Evaporator Cooler Roof RepairRoofingCOPP ROOFING & CONSTRUCTION INC.$30,970
Aug 15, 2025NG Back up GeneratorElectrical, low voltage & AV—$2,377,926
Aug 15, 2025Security Fence UpgradeBuildings & facilitiesTHREE PEAKS CORP.$492,864
Apr 23, 2025Surveillance CameraOtherEVERON LLC$261,374
Dec 5, 2024Evaporator CoolersOther—$100,900
Jun 24, 2024Bus Wash Drain LineOther——
Feb 11, 2024Indio Showroom EnclosureOther——
Jan 30, 2024Permanent FencingBuildings & facilities——
Sep 25, 2023Access Control ProjectElectrical, low voltage & AV——
Aug 21, 2023Coachella Bus HubOther——
Jul 31, 2023Parallelogram Lift ReplacementOther——
Nov 4, 2022Liquid Hydrogen StationOther——
May 9, 2022Building and Modular Trailer DemolitionDemolition & site work——
Jul 14, 2021East Valley Bus Stop ImprovementsOther——
Dec 20, 2020Phase II Beautification InstallationOther——
Nov 19, 2020Floor ResurfacingPaving & streets——
Nov 8, 2020West Valley Refueled Bus Stops ProjectOther——
Aug 19, 2020Wall DemoOther——
Jul 28, 2020CNG Project DemolitionDemolition & site work——
Jul 17, 2020Asphalt Slurry SealPaving & streets——
Jul 14, 2020Fall Arrest SystemOther——
Jun 30, 2020Indio Facility FF&EBuildings & facilities——
Apr 28, 2020Indio Facility ImprovementsBuildings & facilities——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.