528 public works projects registered with the California Department of Industrial Relations, 2000–2026 · Redding, Shasta County. Reported contract value: $113,700,768.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 27 | $44,476,405 |
| 2025 | 33 | $53,246,685 |
| 2024 | 24 | $15,977,678 |
| 2023 | 35 | — |
| 2022 | 41 | — |
| 2021 | 29 | — |
| 2020 | 40 | — |
| 2019 | 19 | — |
| 2018 | 34 | — |
| 2017 | 25 | — |
| 2016 | 41 | — |
| 2015 | 118 | — |
| 2014 | 22 | — |
| 2013 | 16 | — |
| 2012 | 21 | — |
| 2001 | 1 | — |
| 2000 | 1 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Sewer & wastewater · 172
- Other · 56
- Paving & streets · 48
- Water · 41
- Design, inspection & consulting · 39
- Traffic & signals · 30
- Storm drain & flood control · 29
- Electrical, low voltage & AV · 25
- Buildings & facilities · 22
- Bridges & structures · 14
- Parks, landscape & fields · 13
- Roofing · 13
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| J F SHEA CONSTRUCTION INC | 5 | $9,664,460 |
| RTA CONSTRUCTION INC | 3 | $6,880,125 |
| JEFFERSON STATE HIGHWAYS INC | 3 | $633,274 |
| GHD INC | 3 | $443,000 |
| TULLIS INC | 2 | $3,190,015 |
| M5 EXCAVATION | 2 | $1,143,115 |
| PACE Engineering, Inc. | 2 | $532,116 |
| Zeis Construction | 2 | $464,127 |
| SHASTA COUNTY SEPTIC SERVICES | 2 | $363,190 |
| World Telecom & Surveillance, Inc. | 2 | $169,428 |
| INFINITY ABATEMENT SERVICES | 2 | $39,000 |
| AXNER EXCAVATING INC | 1 | $273,456 |
| ADDY SOLAR | 1 | $243,686 |
| CONCENTRIC CONCRETE INC | 1 | $240,895 |
| ELECTRIC POWER SYSTEMS INTERNATIONAL INC | 1 | $58,880 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Oct 2, 2026 | Geotech Eng Services Copper Creek SewerDesign, inspection & consulting | BAJADA GEOSCIENCES, INC. | $25,700 |
| Sep 28, 2026 | Water Storage Tank Repair & MaintenanceOther | SUPERIOR TANK SOLUTIONS INC | $12,201,000 |
| Aug 12, 2026 | On Call CM Services Sacramento RiverParks, landscape & fields | GHD INC | $120,000 |
| Aug 10, 2026 | Cape Seal 2026Paving & streets | AMERICAN PAVEMENT SYSTEMS INC | $1,697,780 |
| Jul 31, 2026 | Installation Bioclean Full Capture InletPaving & streets | N & T DIGMORE INC | $55,990 |
| Jul 31, 2026 | CM Services Replace AC Surfacing 2026Other | GHD INC | $252,000 |
| Jul 22, 2026 | Sacramento River Trail Overlook ProjParks, landscape & fields | JEFFERSON STATE HIGHWAYS INC | $546,734 |
| Jul 22, 2026 | SWWTP Clarifiers 1 & 2 RehabilitationSewer & wastewater | RTA CONSTRUCTION INC | $2,590,000 |
| Jul 14, 2026 | On Call Services for Various ProjectsWater | GHD INC | $71,000 |
| Jul 9, 2026 | Cape Seal 2026 CM ServicesOther | MARK THOMAS & COMPANY, INC. | $420,000 |
| Jul 2, 2026 | Corp Yard West Access Gate ProjectOther | JEFFERSON STATE HIGHWAYS INC | $29,070 |
| Jun 25, 2026 | 2171 Hartnell Ave Demo ProjectDemolition & site work | INFINITY ABATEMENT SERVICES | $19,500 |
| Jun 25, 2026 | Belladonna Storm Drain GradingStorm drain & flood control | Zeis Construction | $44,950 |
| Jun 17, 2026 | Material Recovery Facility Sorter Equip.Buildings & facilities | CP MANUFACTURING LLC | $5,479,700 |
| Jun 16, 2026 | CCWWTP Bldg 21 Switchboard & MCC ProjectSewer & wastewater | ENERGY INNOVATIONS | $995,000 |
| Jun 16, 2026 | Magnums Area Remote Sewer ProjectSewer & wastewater | HARDIMAN CONSTRUCTION INC DBA TRENCHLESS TITAN | $3,485,530 |
| Jun 3, 2026 | Mistletoe and Victor Water ImprovementsWater | GILES EXCAVATING AND PAVING INC | $1,615,072 |
| May 8, 2026 | CCWWTP 2026 Sludge Dredging ProjectSewer & wastewater | SYNAGRO-WWT, INC | $335,007 |
| May 8, 2026 | Hartnell Demolition Abandoned FacilityWater | INFINITY ABATEMENT SERVICES | $19,500 |
| May 5, 2026 | Country Oaks Water Main ReplacementWater | ALLEN GILL CONSTRUCTION, INC. | $2,747,792 |
| Apr 7, 2026 | North Willis Area Water Main ImprovementWater | COX AND COX CONSTRUCTION INC. | $4,788,644 |
| Mar 19, 2026 | Stillwater Outfall Building-Phase IISewer & wastewater | CONVERSE CONSTRUCTION INC | $243,041 |
| Feb 20, 2026 | Oregon Street ImprovementsStorm drain & flood control | J F SHEA CONSTRUCTION INC | $1,312,100 |
| Feb 18, 2026 | Westside Rd over Canyon Hollow CreekBridges & structures | J F SHEA CONSTRUCTION INC | $4,748,526 |
| Feb 5, 2026 | Burney Library Roof Replacement SolarRoofing | ADDY SOLAR | $243,686 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.