North Marin Water District

83 public works projects registered with the California Department of Industrial Relations, 2014–2026 · Novato, Marin County. Reported contract value: $1,776,056.

Projects by year

YearProjectsReported contract value
20261$32,740
20253$1,708,316
20241—
20237—
20225—
20214—
20203—
20192—
20184—
201721—
201613—
201516—
20142—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 29
  • Paving & streets · 20
  • Water · 16
  • Bridges & structures · 4
  • Sewer & wastewater · 4
  • Concrete & masonry · 3
  • Buildings & facilities · 3
  • Traffic & signals · 1
  • HVAC & mechanical · 1
  • Electrical, low voltage & AV · 1
  • Parks, landscape & fields · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
TEAM GHILOTTI INC4$1,696,056
ARGONAUT CONSTRUCTORS INC1$80,000

Latest projects

DateProjectPrime contractorContract amount
Sep 22, 2026Emergency Repair - Hwy 101 & 37WaterTEAM GHILOTTI INC$32,740
Sep 22, 2025San Andreas PavingPaving & streetsARGONAUT CONSTRUCTORS INC$80,000
May 20, 2025San Mateo Tank Transmission MainElectrical, low voltage & AVTEAM GHILOTTI INC$1,321,417
May 7, 2025Cherry Hill PS Retaining Wall RepairBridges & structuresTEAM GHILOTTI INC$306,899
Apr 1, 2024NMWD HQ RW Extension from Redwood BlvdWater——
Nov 19, 2023Crest Pump StationWater——
Nov 5, 2023Gallagher Well No. 1 RehabilitationWater——
Oct 31, 2023North Marin Aqueduct Manway InstallWater——
Oct 23, 2023Oceana Marin Wastewater Treatment and StSewer & wastewater——
Aug 10, 2023Supernatant Line Replacement Phase 1 & 2Buildings & facilities——
Jun 12, 2023NMWD Corporate Yard PavingPaving & streets——
Jun 12, 2023NMWD Corporate Yard PavingPaving & streets——
Jun 15, 2022NMWD Admin & Lab UpgradeOther——
Jun 15, 2022NMWD Admin & Lab UpgradeOther——
Mar 29, 2022STP Chemical System Upgrades -Tank R&ROther——
Feb 24, 2022Misc Traffic ControlTraffic & signals——
Feb 14, 2022New Gallagher Well No. 2Water——
Jun 28, 2021Old Ranch Road Tank No. 2Paving & streets——
Apr 23, 2021Replace 810 ft 6 in AC Pipe on Glen RdOther——
Mar 31, 2021STP Coat Top of Concrete ClearwellsConcrete & masonry——
Mar 26, 2021Grant Ave CI Main Repl w/PVCOther——
May 15, 2020PB Repl-State Route One,CaltransOther——
May 1, 2020Gallagher Ranch Streambank StabilizationBridges & structures——
Jan 17, 2020PRE Tank 4A ReplacementOther——
Oct 17, 2019Cherry Hill Tank No. 2 Recoat & RehabOther——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.