Valley of the Moon Water District

41 public works projects registered with the California Department of Industrial Relations, 2016–2026 · Sonoma, Sonoma County. Reported contract value: $5,331,454.

Projects by year

YearProjectsReported contract value
20261$122,685
20252$35,547
20242$75,348
20236—
202210—
20213—
20202—
20193—
20182—
20172—
20161—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 16
  • Water · 10
  • Paving & streets · 5
  • Parks, landscape & fields · 3
  • Solar, EV & energy · 2
  • Plumbing & restrooms · 2
  • Traffic & signals · 1
  • Bridges & structures · 1
  • HVAC & mechanical · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
WEEKS DRILLING AND PUMP COMPANY2$568,877
CRATUS INC.1$2,787,315
EURO STYLE MANAGEMENT1$774,000
Jacob Vavricka1$122,685
R H & SONS WATER SERVICES1$88,300
Gaya Coating Consulting, Inc.1$29,532
STRIPE 'N' SEAL INC DBA AARON PAVING & SNS ASPHALT SERVICES1$26,665
RESTORATION MANAGEMENT COMPANY1$8,882

Latest projects

DateProjectPrime contractorContract amount
Jul 28, 2026Backflow Prevention Device TestingPlumbing & restroomsJacob Vavricka$122,685
Jul 15, 2025Corp Yard and Office Asphalt MaintenancePaving & streetsSTRIPE 'N' SEAL INC DBA AARON PAVING & SNS ASPHALT SERVICES$26,665
Mar 17, 2025Water Cooler LeakOtherRESTORATION MANAGEMENT COMPANY$8,882
Sep 16, 2024ASR Pilot Test AppurtenanceOther—$75,348
Apr 30, 20243021 PavingPaving & streets——
Dec 3, 2023Glen Ellen Transmission and Fire Flow ImPaving & streets——
May 1, 2023Park Well ASRWater——
May 1, 2023Chestnut Exploratory Well DrillingWater——
May 1, 2023Park Well RedrillWater——
May 1, 2023Verano Well ASRWater——
Feb 23, 2023Solar and EV Plug InstallationSolar, EV & energy——
Nov 8, 2022Glen Ellen Transmission and Fire Flow ImOther——
Nov 8, 2022Glen Ellen Transmission and Fire Flow ImOther——
Nov 6, 2022Valve Replacement ProgramOther——
Sep 27, 2022Glen Ellen Transmission and Fire Flow ImOther——
Jun 22, 2022Kearney Site Clean UpParks, landscape & fields——
Apr 27, 2022Re-drill Park WellWater——
Mar 24, 2022VOIDOther——
Feb 14, 2022Larbre/Pedroncelli WellsTraffic & signals——
Feb 9, 2022Corp Yard PavingPaving & streets——
Jan 31, 2022Corp Yard PavingPaving & streets——
Sep 27, 2021Replace Signs at Office/YardOther——
Aug 17, 2021Saddle Tank LandscapeParks, landscape & fields——
Jan 18, 2021Main ReplacementOther——
Dec 1, 2020Main ReplacementOther——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.