Eureka Union School District
97 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Granite Bay, Placer County. Reported contract value: $1,309,517.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 5 | $280,564 |
| 2025 | 8 | $857,622 |
| 2024 | 3 | $112,959 |
| 2023 | 11 | $58,372 |
| 2022 | 5 | — |
| 2021 | 2 | — |
| 2019 | 2 | — |
| 2018 | 3 | — |
| 2017 | 13 | — |
| 2016 | 16 | — |
| 2015 | 28 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 22
- Buildings & facilities · 17
- Roofing · 11
- Paving & streets · 10
- Parks, landscape & fields · 10
- Painting & flooring · 7
- Plumbing & restrooms · 5
- HVAC & mechanical · 5
- Electrical, low voltage & AV · 4
- Concrete & masonry · 3
- Sewer & wastewater · 1
- Fire & life safety · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| RUA & SON MECHANICAL INCORPORATED | 4 | $279,899 |
| CREATIVE BUILDERS | 4 | $179,279 |
| COLLINS ELECTRICAL COMPANY, INC. | 3 | $359,738 |
| PLACER BUILDING CONTRACTORS INC | 2 | $103,260 |
| DAVE BANG ASSOCIATES INCORPORATED OF CALIFORNIA | 1 | $129,952 |
| WEST COAST | 1 | $123,010 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Sep 16, 2026 | Maidu - New Outside LED LightsStorm drain & flood control | COLLINS ELECTRICAL COMPANY, INC. | $36,647 |
| May 12, 2026 | Greenhills TK Play Area Add OnOther | CREATIVE BUILDERS | $17,963 |
| Feb 12, 2026 | Olympus Jr. High - Room F3 and F4 RepairOther | WEST COAST | $123,010 |
| Feb 5, 2026 | Maidu 5-12 Play Structure InstallationParks, landscape & fields | CREATIVE BUILDERS | $63,607 |
| Jan 7, 2026 | Maidu 2-5 Play Structure InstallationParks, landscape & fields | CREATIVE BUILDERS | $39,337 |
| Oct 28, 2025 | Eureka School Rm 18 Roof Leak RepairRoofing | RUA & SON MECHANICAL INCORPORATED | $28,238 |
| Oct 24, 2025 | Greenhills Portables Roof RepairRoofing | RUA & SON MECHANICAL INCORPORATED | $158,581 |
| Jul 1, 2025 | Oakhills PlaygroundParks, landscape & fields | DAVE BANG ASSOCIATES INCORPORATED OF CALIFORNIA | $129,952 |
| Jun 11, 2025 | Excelsior Gym LED UpgradeElectrical, low voltage & AV | COLLINS ELECTRICAL COMPANY, INC. | $29,941 |
| May 7, 2025 | Greenhills Fire Alarm System ConduitFire & life safety | COLLINS ELECTRICAL COMPANY, INC. | $293,150 |
| Mar 28, 2025 | Cavitt Jr High Shade Structure ConcreteConcrete & masonry | PLACER BUILDING CONTRACTORS INC | $51,630 |
| Mar 28, 2025 | Oakhills Shade Structure ConcreteConcrete & masonry | PLACER BUILDING CONTRACTORS INC | $51,630 |
| Mar 12, 2025 | Maidu F Portables Roof ReplacementRoofing | — | $114,500 |
| Dec 9, 2024 | Cavitt Girls Locker Room Roof RepairRoofing | RUA & SON MECHANICAL INCORPORATED | $48,680 |
| Nov 8, 2024 | Excelsior MPR New RoofRoofing | RUA & SON MECHANICAL INCORPORATED | $44,400 |
| Jun 14, 2024 | Cavitt JHS Illuminated SignOther | — | $19,879 |
| Dec 30, 2023 | Cavitt Install Shade StructuresBuildings & facilities | — | — |
| Dec 18, 2023 | Oakhills/Ridgeview Install Shade StructuBuildings & facilities | — | — |
| Dec 17, 2023 | Cavitt English Building Roof RepairRoofing | — | — |
| Dec 17, 2023 | Greenhills Install Shade and PlaygroundParks, landscape & fields | — | — |
| Nov 20, 2023 | Ridgeview Basketball PostsBuildings & facilities | CREATIVE BUILDERS | $58,372 |
| Nov 19, 2023 | Excelsior Light FixturesOther | — | — |
| Nov 1, 2023 | Maidu School Shade StructuresBuildings & facilities | — | — |
| Sep 4, 2023 | Maidu School Shade StructuresBuildings & facilities | — | — |
| Aug 28, 2023 | Eureka Board Room AV SystemElectrical, low voltage & AV | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.