46 public works projects registered with the California Department of Industrial Relations, 2015–2023 · Sacramento.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2023 | 2 | — |
| 2022 | 2 | — |
| 2020 | 3 | — |
| 2019 | 4 | — |
| 2018 | 3 | — |
| 2017 | 20 | — |
| 2016 | 7 | — |
| 2015 | 5 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 11
- Buildings & facilities · 9
- Electrical, low voltage & AV · 6
- Painting & flooring · 6
- Demolition & site work · 3
- Fire & life safety · 2
- HVAC & mechanical · 2
- Elevators & conveying · 2
- Solar, EV & energy · 1
- Plumbing & restrooms · 1
- Parks, landscape & fields · 1
- Paving & streets · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jan 25, 2023 | Elevator ModernizationElevators & conveying | — | — |
| Jan 24, 2023 | KDM 160, 160B and 264Demolition & site work | — | — |
| Sep 21, 2022 | Calaveras hall 128 and 132Buildings & facilities | — | — |
| Jan 26, 2022 | Sierra Hall Suite 160 CarpetPainting & flooring | — | — |
| May 20, 2020 | JOCOther | — | — |
| May 20, 2020 | JOCOther | — | — |
| May 20, 2020 | JOCOther | — | — |
| Dec 12, 2019 | Regional JOC - Outback 19Other | — | — |
| Jul 8, 2019 | Public WorksOther | — | — |
| Jul 8, 2019 | Telecom Data Wiring Services 2019Electrical, low voltage & AV | — | — |
| Feb 15, 2019 | Job Order ContractOther | — | — |
| Jun 13, 2018 | Flooring Systems 2018Painting & flooring | — | — |
| May 14, 2018 | Library Testing Center & Art StorageBuildings & facilities | — | — |
| Jan 11, 2018 | Flooring Systems 2018Painting & flooring | — | — |
| Oct 24, 2017 | Soccer/Softball Restroom & Concession BuPlumbing & restrooms | — | — |
| Sep 21, 2017 | Eureka Hall Data Cabling UpgradesElectrical, low voltage & AV | — | — |
| Sep 4, 2017 | Police Building Fire Rated Corridor CorrBuildings & facilities | — | — |
| Sep 1, 2017 | Folsom Hall Speech Pathology Ph. II ImprBuildings & facilities | — | — |
| Jul 26, 2017 | Dining Commons Exterior PaintingPainting & flooring | — | — |
| Jul 24, 2017 | Folsom Hall Speech Pathology T.I.s Ph. 1Buildings & facilities | — | — |
| Jul 10, 2017 | Job Order ContractOther | — | — |
| Jun 15, 2017 | Science II BuildingBuildings & facilities | — | — |
| May 22, 2017 | Jenkins Hall Interior RenovationBuildings & facilities | — | — |
| May 15, 2017 | Steel Sectional DoorBuildings & facilities | — | — |
| May 8, 2017 | Regional JOC - RoofingRoofing | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.