South Coast Water District
72 public works projects registered with the California Department of Industrial Relations, 2024–2026 · Laguna Beach, Orange County. Reported contract value: $38,436,782.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 21 | $15,219,576 |
| 2025 | 27 | $10,216,601 |
| 2024 | 24 | $13,000,606 |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 17
- Sewer & wastewater · 14
- Water · 14
- Paving & streets · 11
- Buildings & facilities · 3
- Demolition & site work · 3
- Electrical, low voltage & AV · 2
- Design, inspection & consulting · 2
- HVAC & mechanical · 2
- Plumbing & restrooms · 1
- Painting & flooring · 1
- Concrete & masonry · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| BIG BEN INC | 4 | $4,050,024 |
| GILES ENGINEERING | 4 | $3,226,714 |
| CHI CONSTRUCTION | 3 | $5,714,840 |
| T E ROBERTS INC | 3 | $3,725,863 |
| FERREIRA CONSTRUCTION CO INC | 3 | $2,323,654 |
| Vicon Enterprise Inc | 3 | $1,374,182 |
| WESTERN A/V | 3 | $49,363 |
| CORA CONSTRUCTORS INC | 2 | $1,374,400 |
| MIKE PRLICH & SONS INC | 2 | $800,000 |
| FILANC | 2 | $800,000 |
| GCI CONSTRUCTION INC | 2 | $600,000 |
| WILLSCOT | 2 | $184,300 |
| ALPHA STRUCTURAL INC | 2 | $52,145 |
| FARWEST CORROSION CONTROL COMPANY | 2 | $15,945 |
| ARMOR FENCE CONCEPTS INC | 1 | $97,818 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Sep 17, 2026 | Additional Emergency Barricade WallDemolition & site work | ALPHA STRUCTURAL INC | $35,926 |
| Sep 10, 2026 | Emergency Barricade Installation ProtectSewer & wastewater | ALPHA STRUCTURAL INC | $16,219 |
| Jul 22, 2026 | Calle Agua- Buried Fence OptionBuildings & facilities | ARMOR FENCE CONCEPTS INC | $97,818 |
| Jul 9, 2026 | Del Obispo Recycled Water Expansion ProjWater | CHI CONSTRUCTION | $5,114,840 |
| Jul 9, 2026 | Pump Station 6 Improvements ProjectWater | CORA CONSTRUCTORS INC | $1,214,000 |
| Jul 1, 2026 | Emergency Repair of HVAC Unit @ LS6HVAC & mechanical | ACCO ENGINEERED SYSTEMS | $16,716 |
| Jun 11, 2026 | JRWSS On-Call Emergency Construction SrvSewer & wastewater | T E ROBERTS INC | $500,000 |
| Jun 11, 2026 | 26-0027ASewer & wastewater | FILANC | $500,000 |
| Jun 11, 2026 | JRWSS On-Call Emergency Construction SrvSewer & wastewater | W A RASIC CONSTRUCTION COMPANY INC | $500,000 |
| Jun 11, 2026 | JRWSS On-Call Emergency Construction SrvSewer & wastewater | MIKE PRLICH & SONS INC | $500,000 |
| Jun 11, 2026 | JRWSS On-Call Emergency construction SrvSewer & wastewater | GILES ENGINEERING | $500,000 |
| May 14, 2026 | LTM Mateo Flow Control Vault ImprvmntsOther | CORA CONSTRUCTORS INC | $160,400 |
| May 11, 2026 | 2026 Dana Point Water Service RplcmntWater | GILES ENGINEERING | $1,144,985 |
| Mar 27, 2026 | Sewer Point RepairsSewer & wastewater | GILES ENGINEERING | $17,244 |
| Mar 12, 2026 | Holly Drive Sewer Replacement ProjectSewer & wastewater | Torres Sanitation Systems Construction | $205,500 |
| Mar 12, 2026 | Engineering Design Srvcs for Res 5A-1Design, inspection & consulting | Ardurra Group, Inc. | $160,235 |
| Mar 12, 2026 | JRWSS JTM U3R6 RELOCATION RITZ POINTE DRPaving & streets | T E ROBERTS INC | $2,925,863 |
| Mar 3, 2026 | Internal Cathodic Protection InspectionOther | FARWEST CORROSION CONTROL COMPANY | $9,585 |
| Mar 2, 2026 | DHTC Tennis Courts Resurfacing (1&2)Paving & streets | TRUELINE CONSTRUCTION & SURFACING INC DBA TRUELINE | $29,400 |
| Feb 26, 2026 | 26 Annual Cathodic Protection Survey WTPOther | FARWEST CORROSION CONTROL COMPANY | $6,360 |
| Jan 8, 2026 | PCH PRV Replacement ProjectWater | GILES ENGINEERING | $1,564,484 |
| Nov 5, 2025 | JRWSS JTM U3R5 Air/Vacuum Valve RelocatiOther | FERREIRA CONSTRUCTION CO INC | $255,000 |
| Oct 16, 2025 | SS Lateral Inspection for Mission HospitSewer & wastewater | MATTUCCI PLUMBING INC | $6,668 |
| Oct 16, 2025 | West Street Restrooms 2nd Floor ProjectPaving & streets | — | $115,000 |
| Oct 16, 2025 | Laguna Cliffs Marriott Fire Flow ImproveParks, landscape & fields | FERREIRA CONSTRUCTION CO INC | $2,047,669 |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.