Rialto USD
22 public works projects registered with the California Department of Industrial Relations, 2013–2017 · Rialto.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2017 | 1 | — |
| 2016 | 8 | — |
| 2015 | 7 | — |
| 2014 | 4 | — |
| 2013 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Demolition & site work · 5
- Design, inspection & consulting · 4
- Buildings & facilities · 4
- Other · 3
- Electrical, low voltage & AV · 3
- Bridges & structures · 1
- Elevators & conveying · 1
- Parks, landscape & fields · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 14, 2017 | Rialto Cable Trench EdisonOther | — | — |
| Dec 18, 2016 | Solar Shade Structures - Phase 1Design, inspection & consulting | — | — |
| Dec 7, 2016 | relocatable classrooms in Boyd, Dunn, DoDemolition & site work | — | — |
| Dec 7, 2016 | EHS Stdium Reconstruction - Track and FiParks, landscape & fields | — | — |
| Dec 4, 2016 | Solar Energy Project - Phase 1Design, inspection & consulting | — | — |
| Nov 6, 2016 | improvement of pedestrian safety to WernOther | — | — |
| Oct 6, 2016 | relocatable classrooms in Dunn ESDemolition & site work | — | — |
| Oct 6, 2016 | relocatable classrooms in Dollahan ESDemolition & site work | — | — |
| Oct 6, 2016 | relocatable classrooms in Boyd ESDemolition & site work | — | — |
| Sep 14, 2015 | Eisenhower High SchoolBuildings & facilities | — | — |
| Jul 27, 2015 | Eisenhower High School Pylon SignBuildings & facilities | — | — |
| Jul 16, 2015 | Eisenhower High SchoolBuildings & facilities | — | — |
| Jun 18, 2015 | Eisenhower High SchoolDesign, inspection & consulting | — | — |
| Jun 15, 2015 | Carter High School Track and Field ImproBridges & structures | — | — |
| Jun 8, 2015 | Relocation of 3 Portable Classrooms - CaDemolition & site work | — | — |
| Jun 3, 2015 | Energy Expenditure Plan No. 2, energy upElectrical, low voltage & AV | — | — |
| Nov 2, 2014 | Jehue Middle School Classroom AdditionBuildings & facilities | — | — |
| Nov 2, 2014 | Design, Engineering, HVAC Replacement, CDesign, inspection & consulting | — | — |
| Jun 23, 2014 | Kelley Elementary School and Kucera MiddElevators & conveying | — | — |
| Feb 12, 2014 | CNG Fueling StationOther | — | — |
| Dec 2, 2013 | EHS Electrical & Gas Upgrade , Phase IIIElectrical, low voltage & AV | — | — |
| Jun 3, 2013 | EISENHOWER HIGH SCHOOL SITE ELECTRICAL &Electrical, low voltage & AV | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.