Department of Parks and Recreation Santa Cruz District
47 public works projects registered with the California Department of Industrial Relations, 2019–2026 · Felton, Santa Cruz County. Reported contract value: $2,057,458.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 4 | $439,101 |
| 2025 | 5 | $835,102 |
| 2024 | 5 | $783,255 |
| 2023 | 13 | — |
| 2022 | 11 | — |
| 2020 | 6 | — |
| 2019 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Storm drain & flood control · 11
- Paving & streets · 8
- Parks, landscape & fields · 7
- Buildings & facilities · 6
- Demolition & site work · 5
- Sewer & wastewater · 2
- Other · 2
- Painting & flooring · 2
- Roofing · 2
- Solar, EV & energy · 1
- Bridges & structures · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| BEST BUILT INC | 2 | $126,000 |
| DURABLE COOL ROOFS INC | 1 | $215,145 |
| MERZ BROS CONSTRUCTION INC | 1 | $188,500 |
| BNO BUILDERS INC | 1 | $95,000 |
| GRAHAM CONTRACTORS INC | 1 | $69,460 |
| BETZ WORKS INC | 1 | $36,880 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| May 14, 2026 | Wilder Bunkhouse ReroofingBuildings & facilities | BNO BUILDERS INC | $95,000 |
| Apr 23, 2026 | C25715002 - Agua Puera Creek RestorationDemolition & site work | — | $193,641 |
| Apr 7, 2026 | Henry Cowell State Park EV ChargersSolar, EV & energy | BEST BUILT INC | $81,000 |
| Mar 2, 2026 | 25/26 Districtwide Paving ContractStorm drain & flood control | GRAHAM CONTRACTORS INC | $69,460 |
| Nov 24, 2025 | C25715018 - Culverts and HandrailsStorm drain & flood control | BETZ WORKS INC | $36,880 |
| Oct 24, 2025 | C25715014 - Hydropneumatic Tank ReplacemParks, landscape & fields | MERZ BROS CONSTRUCTION INC | $188,500 |
| Jun 3, 2025 | Structure ReroofingBridges & structures | DURABLE COOL ROOFS INC | $215,145 |
| Apr 3, 2025 | Saddle Mountain Hotel Plumbing RebuildStorm drain & flood control | BEST BUILT INC | $45,000 |
| Mar 13, 2025 | SCD Paving Contract 24/25Paving & streets | — | $349,577 |
| Aug 1, 2024 | C23715038 23/24 Lodge Road Vegetation MaPaving & streets | — | — |
| Jul 29, 2024 | C24715012 Trail Rebuilding, Fuel Reduct.Parks, landscape & fields | — | $783,255 |
| May 1, 2024 | C23715031 Lead Abatement of an EmployeeDemolition & site work | — | — |
| Apr 1, 2024 | C23715016 Lead Abatement and Painting ofDemolition & site work | — | — |
| Apr 1, 2024 | C23715020 23/24 District Paving ContractPaving & streets | — | — |
| Nov 1, 2023 | C23715001 Districtwide On-call Tree ServParks, landscape & fields | — | — |
| Jul 1, 2023 | C22715004 Prep and Paint 2 State ResidenPainting & flooring | — | — |
| Jul 1, 2023 | C23715013 Summit Drive Tree RemovalParks, landscape & fields | — | — |
| May 25, 2023 | C23715017 2023 Winter Storm Big Basin EmStorm drain & flood control | — | — |
| Apr 25, 2023 | C22715043 Nisene Marks Emergency LandsliOther | — | — |
| Apr 12, 2023 | A23715005 Lighthouse WindowsBuildings & facilities | — | — |
| Apr 1, 2023 | C22715003 Summit Drive Hazard Tree RemovParks, landscape & fields | — | — |
| Mar 30, 2023 | C22715007 22/23 District Paving ContractPaving & streets | — | — |
| Mar 23, 2023 | C22715044 2023 Winter Storm Damage EmergStorm drain & flood control | — | — |
| Feb 14, 2023 | C22715045 2023 Winter Storm Damage RepaiStorm drain & flood control | — | — |
| Feb 11, 2023 | C22715038 2023 Winter Storm Damage RepaiStorm drain & flood control | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.