Montecito Water District

60 public works projects registered with the California Department of Industrial Relations, 2016–2026 · Santa Barbara, Santa Barbara County. Reported contract value: $14,312,151.

Projects by year

YearProjectsReported contract value
20262$893,250
20255$11,278,173
20243$1,816,300
202313$324,429
20224—
20216—
20207—
20194—
201812—
20171—
20162—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Water · 24
  • Other · 12
  • Storm drain & flood control · 7
  • Bridges & structures · 6
  • Paving & streets · 5
  • Parks, landscape & fields · 2
  • Electrical, low voltage & AV · 2
  • Buildings & facilities · 1
  • Concrete & masonry · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
PACIFIC HYDROTECH CORPORATION2$10,972,200
AMERICAN PIPELINE SERVICES2$2,559,550
Wood Rodgers Inc1$150,000
SECUREPRO INC1$140,000
ESAU LANDSCAPES1$124,000
CHALLENGE ASPHALT INC1$41,973

Latest projects

DateProjectPrime contractorContract amount
Aug 31, 2026Highline Segment 2 DesignOtherWood Rodgers Inc$150,000
Jun 24, 2026Highline Repair at Bella VistaOtherAMERICAN PIPELINE SERVICES$743,250
Oct 9, 2025DOULTON DRIVEWAYPaving & streetsCHALLENGE ASPHALT INC$41,973
Sep 18, 2025Terminal Reservoir Seismic RetrofitWaterPACIFIC HYDROTECH CORPORATION$6,382,500
Jul 2, 2025Park Lane Reservoir Seismic RetrofitWaterPACIFIC HYDROTECH CORPORATION$4,589,700
May 21, 2025Jameson Camera Installation & MonitoringElectrical, low voltage & AVSECUREPRO INC$140,000
May 20, 2025Montecito Water Demonstration GardenParks, landscape & fieldsESAU LANDSCAPES$124,000
Jun 25, 2024Freehaven & Las Tunas Water Main ReplaceWaterAMERICAN PIPELINE SERVICES$1,816,300
Apr 24, 2024Replace Dry Barrel Fire Hydrants VariousWater——
Apr 1, 2024Office PavingPaving & streets——
Dec 13, 2023Highline Repair at Bella VistaStorm drain & flood control—$324,429
Sep 18, 2023La Vereda Lane Water Main ReplacementWater——
Sep 15, 2023Buena Vista Water Main ReplacementWater——
Sep 15, 2023Monte Cristo Water Main ReplacementWater——
Jun 19, 20232332 Bella Vista Main RepairOther——
Jun 12, 2023Water Main Relocation at the US101 and FWater——
Apr 24, 2023San Ysidro Roundabout Water Main RelocatWater——
Apr 17, 2023ORTEGA LEAK REPAIRSOther——
Apr 7, 2023Districtwide Patch PavingWater——
Mar 27, 2023Montecito Water District Collector PoleOther——
Feb 23, 2023Juncal Pipe Repair ProjectStorm drain & flood control——
Feb 22, 2023Jameson Lake Road ClearingStorm drain & flood control——
Feb 10, 2023Juncal Emergency Release ValveStorm drain & flood control——
Dec 15, 2022Office GeneratorElectrical, low voltage & AV——
Jul 18, 2022Olive Mill Roundabout Fire Hydrant RelocWater——