YearProjectsReported contract value
20262$35,646,728
20251$12,844,500
20245$3,702,117
20238—
20225—
20214—
20197—
20184—
20177—
20162—
20151—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Electrical, low voltage & AV · 13
  • Bridges & structures · 10
  • Paving & streets · 6
  • Other · 6
  • Buildings & facilities · 4
  • HVAC & mechanical · 3
  • Demolition & site work · 2
  • Solar, EV & energy · 2
  • Parks, landscape & fields · 2
  • Traffic & signals · 1
  • Design, inspection & consulting · 1
  • Storm drain & flood control · 1

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
LEED ELECTRIC INC1$31,596,942
MANSON CONSTRUCTION CO1$12,844,500
C A RASMUSSEN INC1$4,049,786

Latest projects

DateProjectPrime contractorContract amount
Apr 3, 2026Naval Civil Engineering Labs DemolitionDemolition & site workC A RASMUSSEN INC$4,049,786
Feb 27, 2026South Terminal Shore Power ProjectElectrical, low voltage & AVLEED ELECTRIC INC$31,596,942
Jul 15, 2025Berth 3 (wharf1) Deepening and recon.Bridges & structuresMANSON CONSTRUCTION CO$12,844,500
Dec 31, 2024CA- Port of Hueneme -Volvo LotSolar, EV & energy——
Aug 30, 2024Warehouse 1A Phase 2: Demolition,Bridges & structures—$3,702,117
Apr 17, 2024Ring Road Phase 2Paving & streets——
Jan 14, 2024Joint Operations and Security Center AdmBuildings & facilities——
Jan 8, 2024Temporary Outdoor Vehicle Storage FaciliOther——
Dec 17, 2023Port of Hueneme Main Entrance Security GOther——
Nov 5, 2023Port of Hueneme Landscape ProjectParks, landscape & fields——
Aug 28, 2023NBVC Port Hueneme Wharves 5 and 6 LightiElectrical, low voltage & AV——
Jul 17, 2023Port of Hueneme East End Bathroom DemoDemolition & site work——
Jul 1, 2023Building 448 HVAC ProjectHVAC & mechanical——
Jun 22, 2023Ring Road Pavement Repair Phase 1Paving & streets——
Jun 1, 2023Port Hueneme - 319 Skylights ProjectBuildings & facilities——
May 4, 2023Temporary Office SpaceBuildings & facilities——
Nov 1, 2022Port SweepingStorm drain & flood control——
Oct 3, 2022Utility DockBridges & structures——
Aug 1, 2022Warehouse 1A Demolition Phase 1 ElectricElectrical, low voltage & AV——
May 2, 2022Wharves 5 and 6 Lighting Geotechnical SuElectrical, low voltage & AV——
Jan 23, 2022South Terminal Crane Electrification PowElectrical, low voltage & AV——
Aug 30, 2021Wharf 3 Navy Gate RelocationBridges & structures——
Aug 30, 2021Wharf 3 Navy Gate RelocationBridges & structures——
Feb 28, 2021South Terminal e-UTR Charging Station PoElectrical, low voltage & AV——
Feb 13, 2021The Fixed Camera Infrastructure ProjectElectrical, low voltage & AV——

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.