39 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Cupertino. Reported contract value: $380,366.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 6 | $200,000 |
| 2025 | 1 | $30,000 |
| 2024 | 3 | $33,000 |
| 2023 | 4 | — |
| 2021 | 5 | — |
| 2019 | 1 | — |
| 2018 | 3 | — |
| 2017 | 3 | — |
| 2016 | 3 | — |
| 2015 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 32
- Sewer & wastewater · 4
- Plumbing & restrooms · 3
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| MARK THOMAS & COMPANY, INC. | 3 | $96,000 |
| FLOWING WATER | 2 | $94,366 |
| ABLE MAINTENANCE INC | 2 | $60,000 |
| JB PLUMBING AND ELECTRIC | 2 | $60,000 |
| ROTO-ROOTER SERVICES COMPANY DBA NUROTOCO | 2 | $20,000 |
| EG PLUMBING | 1 | $30,000 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Sep 30, 2026 | BSD FY2026-27 EG PlumbingPlumbing & restrooms | EG PLUMBING | $30,000 |
| Jul 1, 2026 | BSD FY 2026-27 AbleOther | ABLE MAINTENANCE INC | $30,000 |
| Jul 1, 2026 | BSD FY 2026-27 Roto RooterOther | ROTO-ROOTER SERVICES COMPANY DBA NUROTOCO | $10,000 |
| Jul 1, 2026 | BSD FY 2026-27 JB PlumbingPlumbing & restrooms | JB PLUMBING AND ELECTRIC | $30,000 |
| Jul 1, 2026 | BSD FY 2026-27 Mark ThomasOther | MARK THOMAS & COMPANY, INC. | $70,000 |
| Jul 1, 2026 | BSD FY 2026-27 Flowing WaterOther | FLOWING WATER | $30,000 |
| Aug 13, 2025 | BSD FY2025-26 JB PlumbingPlumbing & restrooms | JB PLUMBING AND ELECTRIC | $30,000 |
| Jul 1, 2024 | BSD FY2024-25 AbleOther | — | $10,000 |
| Jul 1, 2024 | BSD FY2024-25 Roto RooterOther | — | $10,000 |
| Jul 1, 2024 | BSD FY2024-25 Mark ThomasOther | MARK THOMAS & COMPANY, INC. | $13,000 |
| Jul 1, 2023 | BSD FY2023-2024 Mark ThomasOther | — | — |
| Jul 1, 2023 | BSD FY2023-2024 Roto RooterOther | — | — |
| Jul 1, 2023 | BSD FY2023-2024 ABLEOther | — | — |
| Jun 26, 2023 | BSD FY2023-2024 AB/JDDOther | — | — |
| Oct 8, 2021 | District Wide Capital Improvement ProjecOther | — | — |
| Jul 1, 2021 | BSD FY2021-2022 AB/JDDOther | — | — |
| Jul 1, 2021 | BSD FY2021-2022 ABLEOther | — | — |
| Jul 1, 2021 | BSD FY2021-2022 Roto RooterOther | — | — |
| Jul 1, 2021 | BSD FY2021-2022 Mark ThomasOther | — | — |
| Jan 3, 2019 | BSD FY 2018-2019 AB/JDDOther | — | — |
| Jul 2, 2018 | BSD FY 2018-2019 AbleOther | — | — |
| Jul 2, 2018 | BSD FY 2018-19 Mark ThomasOther | — | — |
| Jul 2, 2018 | BSD FY 2018-2019 Roto RooterOther | — | — |
| Jul 1, 2017 | BSD FY 2017-18 Mark ThomasOther | — | — |
| Jul 1, 2017 | BSD FY 2017-2018 AbleOther | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.