40 public works projects registered with the California Department of Industrial Relations, 2015–2025 · Hanford, Kings County. Reported contract value: $1,702,250.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2025 | 3 | $681,250 |
| 2024 | 1 | $1,021,000 |
| 2023 | 2 | — |
| 2022 | 1 | — |
| 2021 | 6 | — |
| 2020 | 1 | — |
| 2019 | 4 | — |
| 2018 | 1 | — |
| 2017 | 2 | — |
| 2016 | 14 | — |
| 2015 | 4 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 15
- Buildings & facilities · 8
- Concrete & masonry · 4
- Electrical, low voltage & AV · 3
- Painting & flooring · 3
- Design, inspection & consulting · 3
- Demolition & site work · 2
- Paving & streets · 1
- Plumbing & restrooms · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| CORE BUSINESS INTERIORS | 1 | $467,358 |
| DIGITECH INTEGRATION INC | 1 | $169,537 |
| GEIL ENTERPRISES, INC. | 1 | $44,355 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Dec 1, 2025 | Kart Transit Center - Security CamerasElectrical, low voltage & AV | DIGITECH INTEGRATION INC | $169,537 |
| Dec 1, 2025 | KART Transit Center - Alarm and KeylessBuildings & facilities | GEIL ENTERPRISES, INC. | $44,355 |
| Jul 23, 2025 | KART Transit Center - FurnitureBuildings & facilities | CORE BUSINESS INTERIORS | $467,358 |
| Aug 28, 2024 | Holloway North Parking Lot ConstructionBuildings & facilities | — | $1,021,000 |
| Nov 30, 2023 | KART Transit Center ConstructionBuildings & facilities | — | — |
| Aug 1, 2023 | Bus Terminal ConstructionOther | — | — |
| Aug 1, 2022 | CNG FUELING MAINTENANCE AND REPAIR SERVIOther | — | — |
| Sep 27, 2021 | Cancelled - Duplicate ProjectOther | — | — |
| Jul 1, 2021 | Architectural and Engineering - New TranDesign, inspection & consulting | — | — |
| Jul 1, 2021 | Kings County Area Public Transit CenterBuildings & facilities | — | — |
| Mar 29, 2021 | KART Transit Center DemolitionDemolition & site work | — | — |
| Mar 29, 2021 | Asbestos AbatementDemolition & site work | — | — |
| Feb 21, 2021 | New Transit Center - Surveying and MappiDesign, inspection & consulting | — | — |
| Jan 29, 2020 | IMW compressor rebuild and emergency repOther | — | — |
| Jun 3, 2019 | Maintenance Shop Lighting RetrofitElectrical, low voltage & AV | — | — |
| Apr 30, 2019 | CNG Compressor PLC Replace and SoftwareOther | — | — |
| Apr 26, 2019 | Gas Monitoring System ReplacementOther | — | — |
| Apr 22, 2019 | Exterior Painting Bus TerminalPainting & flooring | — | — |
| May 1, 2018 | Asphalt reseal at 629 - Davis St.Paving & streets | — | — |
| Apr 17, 2017 | 504 W 7th st & 610 W 7th St Handrail AltOther | — | — |
| Apr 1, 2017 | 629 Davis St. Concrete R&RConcrete & masonry | — | — |
| Nov 30, 2016 | 504 W. 7th St. Public Restroom AlteratioPlumbing & restrooms | — | — |
| Nov 14, 2016 | 629 Davis St. CNG Detection ServiceOther | — | — |
| Sep 29, 2016 | Concrete pad installs at various locatioConcrete & masonry | — | — |
| Aug 1, 2016 | ADA automatic door operatorBuildings & facilities | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.