110 public works projects registered with the California Department of Industrial Relations, 2015–2026 · Reedley, Fresno County. Reported contract value: $6,034,102.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 1 | $560,250 |
| 2025 | 7 | $1,677,382 |
| 2024 | 9 | $556,950 |
| 2023 | 9 | — |
| 2022 | 12 | — |
| 2021 | 11 | — |
| 2020 | 7 | — |
| 2019 | 6 | — |
| 2018 | 12 | — |
| 2017 | 13 | — |
| 2016 | 12 | — |
| 2015 | 5 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Paving & streets · 34
- Sewer & wastewater · 22
- Other · 13
- Parks, landscape & fields · 8
- Traffic & signals · 5
- Water · 5
- Electrical, low voltage & AV · 4
- Storm drain & flood control · 4
- Plumbing & restrooms · 4
- Buildings & facilities · 3
- Demolition & site work · 2
- Concrete & masonry · 2
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| RUIZ FAMILY ENTERPRISES INC | 3 | $106,009 |
| PRIDE INDUSTRIES ONE, INC. | 1 | $560,250 |
| DON BERRY CONSTRUCTION INC | 1 | $422,355 |
| CENTRAL VALLEY STRIPING | 1 | $246,978 |
| BETTER ENTERPRISES INC | 1 | $232,509 |
| MATTOS UNDERGROUND CONSTRUCTION INC | 1 | $29,642 |
| JOHNSON CONTROLS FIRE PROTECTION LP | 1 | $24,123 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 9, 2026 | Camacho Park Rehab - RR & Snack BarHVAC & mechanical | PRIDE INDUSTRIES ONE, INC. | $560,250 |
| Sep 23, 2025 | Rupert and Church ReconstructionStorm drain & flood control | DON BERRY CONSTRUCTION INC | $422,355 |
| Jul 16, 2025 | Reedley Opera House Stage RevitalizationOther | — | $74,769 |
| May 27, 2025 | Reed Ave & Reedley College Traffic Sig.Traffic & signals | — | $821,435 |
| Apr 10, 2025 | Hope Ave Reconstruction Olson to CurtisPaving & streets | — | $269,161 |
| Mar 20, 2025 | Reedley Opera House Roof Patio/Deck AreaRoofing | — | $58,730 |
| Feb 12, 2025 | WWTP Fiber Optic TerminationSewer & wastewater | — | $1,432 |
| Feb 7, 2025 | WWTP O2 Ditch Retaining WallSewer & wastewater | RUIZ FAMILY ENTERPRISES INC | $29,500 |
| Nov 12, 2024 | Reedley Airport RestroomPlumbing & restrooms | BETTER ENTERPRISES INC | $232,509 |
| Aug 1, 2024 | Airport Trailer Fire SystemFire & life safety | JOHNSON CONTROLS FIRE PROTECTION LP | $24,123 |
| Jul 8, 2024 | WWTP Pavement Maintenance ProjectSewer & wastewater | — | $53,340 |
| Jun 19, 2024 | CDBG 23571 North Avenue ImprovementsPaving & streets | CENTRAL VALLEY STRIPING | $246,978 |
| Jun 3, 2024 | Reedley Sports Park Phase 2Storm drain & flood control | — | — |
| Apr 30, 2024 | Reedley Community Center Asbestos AbatemDemolition & site work | — | — |
| Apr 29, 2024 | Pipeline to Filtration SystemOther | — | — |
| Jan 30, 2024 | Electrical Work for RC TrailerElectrical, low voltage & AV | — | — |
| Jan 30, 2024 | Trailer Electrical ProjectElectrical, low voltage & AV | — | — |
| Dec 11, 2023 | Airport TrailerOther | — | — |
| Dec 10, 2023 | Olson Ave Trunk Line Upsizing Along OlsoSewer & wastewater | — | — |
| Oct 9, 2023 | CDBG 21571 E Street ReconstructionSewer & wastewater | — | — |
| Sep 11, 2023 | Manning Avenue Phase 3Sewer & wastewater | — | — |
| Jul 25, 2023 | TTM 6229 Phase 2Other | — | — |
| Jun 19, 2023 | Manning Ave Pavement Rehab Ph 3 CMPaving & streets | — | — |
| May 9, 2023 | Lift Station Masonry EnclosuresSewer & wastewater | — | — |
| Apr 17, 2023 | Engineering Design for Reedley Sports PaOther | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.