UC San Diego Health

329 public works projects registered with the California Department of Industrial Relations, 2011–2026 · San Diego, San Diego County. Reported contract value: $2,117,179.

Projects by year

YearProjectsReported contract value
202615$583,278
202513$1,470,975
20245$62,927
20231—
20224—
20219—
20204—
20199—
201819—
201765—
2016126—
201553—
20132—
20114—

DIR has published contract amounts since July 2024; earlier years count projects only.

Types of work

  • Other · 124
  • Electrical, low voltage & AV · 53
  • Buildings & facilities · 31
  • HVAC & mechanical · 25
  • Painting & flooring · 23
  • Roofing · 18
  • Plumbing & restrooms · 12
  • Sewer & wastewater · 11
  • Storm drain & flood control · 9
  • Fire & life safety · 7
  • Elevators & conveying · 6
  • Water · 4

Inferred by Atriam from each project's name and description, not reported by the agency.

Contractors it awards most

Prime contractorProjectsReported contract value
FIRST MARK CONTRACTING INC6$257,206
B S D BUILDERS INC5$159,825
COUNTYWIDE MECHANICAL SYSTEMS LLC3$165,587
WEATHERPROOFING TECHNOLOGIES INC3$114,725
REYNOLDS CONTRACTING INC2$949,748
ROD FULLER ELECTRIC CORP.1$80,185
T.R.L. Systems, Incorporated1$62,927
NSWC MECHANICAL SERVICE, LLC1$24,729
JOHNSON CONTROLS INC1$12,535

Latest projects

DateProjectPrime contractorContract amount
Jun 5, 2026Simplex 4100ES System Repair & Node StabOtherJOHNSON CONTROLS INC$12,535
May 1, 2026Supply Fan motorwOtherNSWC MECHANICAL SERVICE, LLC$24,729
Apr 28, 2026Room LL-117 Pump ReplacementOtherFIRST MARK CONTRACTING INC$43,671
Apr 28, 2026Room PH-101 Pump ReplacementOtherFIRST MARK CONTRACTING INC$24,068
Apr 15, 2026UCSD Shiley Eye Center Exterior StairsBuildings & facilitiesFIRST MARK CONTRACTING INC$49,061
Apr 15, 2026West Tower 2nd Fl MaintenanceHVAC & mechanicalFIRST MARK CONTRACTING INC$22,035
Apr 14, 2026Epoxy FlooringPainting & flooringFIRST MARK CONTRACTING INC$19,555
Mar 3, 2026UCSD MCEC West Tower 2nd Fl Outpatient CPainting & flooringFIRST MARK CONTRACTING INC$98,816
Jan 30, 2026West Tower - CU 7 Circuit B Coil ReplaceOtherCOUNTYWIDE MECHANICAL SYSTEMS LLC$74,299
Jan 30, 2026CU 7 Circuit A Coil ReplacementOtherCOUNTYWIDE MECHANICAL SYSTEMS LLC$69,438
Jan 29, 2026Helipad Roof-Emergency Leak RepairsRoofingWEATHERPROOFING TECHNOLOGIES INC$38,935
Jan 28, 2026Encapsulate Boiler Chemical TreatmentHVAC & mechanicalCOUNTYWIDE MECHANICAL SYSTEMS LLC$21,850
Jan 23, 20266th Floor Leak Repairs-SOW ContinuedOtherWEATHERPROOFING TECHNOLOGIES INC$37,890
Jan 22, 20266th Floor Emergency Roof Leak RepairsRoofingWEATHERPROOFING TECHNOLOGIES INC$37,900
Jan 8, 2026Line Stop Service EstimateWater—$8,495
Sep 29, 2025UCSD East Roof Door RepairRoofingB S D BUILDERS INC$5,653
Sep 11, 2025UCSD EAST Tower BlowdownHVAC & mechanicalB S D BUILDERS INC$43,665
Aug 26, 2025UCSD Roof Door ReplacementRoofingB S D BUILDERS INC$70,558
Jul 23, 2025Provide & Install 4 Steel Service ValvesOther—$23,410
Jun 13, 2025Replace Comp 1 on AH4Other—$65,640
Jun 9, 2025Provide 3 Spare 25HP CompressorsOther—$61,056
Jun 6, 2025Replace Compressor 2 on AH2Other—$31,594
Jun 6, 2025Replace Both Compressors on AH3Other—$99,517
May 1, 2025Valve ReplacementWaterB S D BUILDERS INC$19,975
Feb 11, 2025UCSD EAST CAMPUS 4th FLOOR PLUMBINGPlumbing & restroomsREYNOLDS CONTRACTING INC$285,000

Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.