| Year | Projects | Reported contract value |
|---|---|---|
| 2024 | 6 | — |
| 2023 | 11 | — |
| 2022 | 8 | — |
| 2021 | 24 | — |
| 2020 | 9 | — |
| 2019 | 4 | — |
| 2018 | 3 | — |
| 2017 | 12 | — |
| 2016 | 1 | — |
| 2015 | 3 | — |
| 2014 | 1 | — |
| 2013 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Other · 22
- Buildings & facilities · 21
- Paving & streets · 11
- Parks, landscape & fields · 9
- Electrical, low voltage & AV · 4
- Roofing · 3
- HVAC & mechanical · 3
- Fire & life safety · 2
- Plumbing & restrooms · 2
- Painting & flooring · 2
- Demolition & site work · 2
- Sewer & wastewater · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Apr 5, 2024 | Vacuum evacuation and disposal of non-haOther | — | — |
| Apr 2, 2024 | Demo existing asphalt and haul off excavPaving & streets | — | — |
| Mar 21, 2024 | John Sutter Middle School Kitchen UpgradBuildings & facilities | — | — |
| Mar 20, 2024 | Fowler High School Kitchen UpgradeBuildings & facilities | — | — |
| Feb 4, 2024 | Installation of 12 bus chargersOther | — | — |
| Jan 18, 2024 | Marshall elementary PS/TK classroomsBuildings & facilities | — | — |
| Dec 26, 2023 | HVAC Replacement Project Malaga/Sutter/HHVAC & mechanical | — | — |
| Nov 3, 2023 | 7 new preschool & transitional kindergarBuildings & facilities | — | — |
| Sep 27, 2023 | grade to remove dirt, planting 220 plantOther | — | — |
| Sep 21, 2023 | Fremont Cafeteria Replacement PrjoectOther | — | — |
| Sep 7, 2023 | dkjslOther | — | — |
| Aug 16, 2023 | Landscaping bondingParks, landscape & fields | — | — |
| Aug 16, 2023 | Landscaping bondingParks, landscape & fields | — | — |
| Aug 2, 2023 | Fremont Elementary Electrical WorkElectrical, low voltage & AV | — | — |
| Mar 9, 2023 | Relocatable Classroom at Fremont ElementBuildings & facilities | — | — |
| Feb 28, 2023 | remove 43,000 SF of asphalt, remove busPaving & streets | — | — |
| Feb 22, 2023 | dkjslOther | — | — |
| Nov 30, 2022 | Malaga Cabinet Upgrades Rm 7,8,12 IMCOther | — | — |
| Aug 11, 2022 | Sidewalk safety in front of Marshall ElePaving & streets | — | — |
| Jul 29, 2022 | Main Electrical Panel ReplacementElectrical, low voltage & AV | — | — |
| Jul 1, 2022 | New Electrical Panel - Malaga ESElectrical, low voltage & AV | — | — |
| Jun 6, 2022 | Install new ADA ramp & remove sidewalkPaving & streets | — | — |
| May 27, 2022 | Early Education CenterSewer & wastewater | — | — |
| May 6, 2022 | Marshall Playground InstallParks, landscape & fields | — | — |
| Mar 15, 2022 | ADA Concrete Sidewalk at New AG CenterPaving & streets | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.