San Gorgonio Pass Water Agency
7 public works projects registered with the California Department of Industrial Relations, 2018–2026 · Beaumont, Riverside County. Reported contract value: $5,075,324.
Projects by year
| Year | Projects | Reported contract value |
|---|---|---|
| 2026 | 2 | $354,197 |
| 2025 | 2 | $4,721,127 |
| 2020 | 1 | — |
| 2018 | 2 | — |
DIR has published contract amounts since July 2024; earlier years count projects only.
Types of work
- Water · 2
- Storm drain & flood control · 2
- Traffic & signals · 1
- Other · 1
- Buildings & facilities · 1
Inferred by Atriam from each project's name and description, not reported by the agency.
Contractors it awards most
| Prime contractor | Projects | Reported contract value |
|---|---|---|
| WEKA INC | 1 | $4,676,332 |
| GLENN CHAVEZ CONSTRUCTION | 1 | $330,980 |
| NATIONAL TRENCH SAFETY TRAFFIC SOLUTIONS | 1 | $23,217 |
Latest projects
| Date | Project | Prime contractor | Contract amount |
|---|---|---|---|
| Jun 1, 2026 | Brookside East Heli-Hydrant FacilityWater | GLENN CHAVEZ CONSTRUCTION | $330,980 |
| Jan 9, 2026 | San Gorgonio Pass Nested Monitoring WellTraffic & signals | NATIONAL TRENCH SAFETY TRAFFIC SOLUTIONS | $23,217 |
| Sep 15, 2025 | County Line Rd Recharge Basin ProjectStorm drain & flood control | WEKA INC | $4,676,332 |
| Apr 15, 2025 | Nested Monitoring Well Mud Haul AwayWater | — | $44,795 |
| Dec 20, 2020 | Fiesta Recharge FacilityStorm drain & flood control | — | — |
| Dec 16, 2018 | Noble Creek EBX Upgrades ProjectOther | — | — |
| Apr 16, 2018 | Beaumont Avenue Recharge Facility & MounBuildings & facilities | — | — |
Source: California Department of Industrial Relations public works project registrations (PWC-100), updated daily by Atriam.